Challenging bridge demolition

DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • Flyover replacement
    February 22, 2012
    French contractor DSD Démolition was one of three firms that worked on the recent demolition of the A55 highway flyover in Marseilles, France. The 20-year-old flyover stood near the harbour and formed part of a main route through Marseille leading to Lyon and Avignon. However, it was an ugly structure and spoiled the city's landscape so as part of the wider regeneration taking part in Marseille's harbour, the 1.3km bridge had to be demolished within three months. DSD Démolition had two operators for each of
  • Productive breaking with Doosan
    April 16, 2012
    The powerful and productive DXB breakers from Doosan are said to suit a wide array of applications such as tunneling, secondary reduction, primary winning and demolition.
  • Crushing and screening for producing and re-using
    July 23, 2012
    The recycling and minerals extraction markets now share technologies, Mike Woof reports Not surprisingly, the Steinexpo quarrying event in Germany was a key launch venue for new crushing and screening technologies, as well as associated quarrying technology. Crushing and screening equipment firms from a wide range of European countries including Austria, the Czech Republic, Germany, Ireland, Italy, Sweden, Switzerland and the UK were present at the exhibition. However it was noticeable how closely the miner
  • Drilling rig meets the utility supply challenge
    April 11, 2012
    A tricky utility supply project has been carried out in difficult conditions in Germany, without disturbing a village access road. The drilling work for the project was operated by boring contractor Beermann and the site was located on a plateau some 5km from the nearest village.