DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • Ardennes Tech brings Fortress shears to French market
    April 26, 2018
    Ardennes Tech has added Fortress mobile shears from ShearCore to its range of attachments. ShearCore's FC series of 'concrete cracker' shears features a narrow stick body for improved visibility for the operator and a removable isolated bottom cover for easy access to all serviceable components. The Fortress FC25 has a shear weight 2,722 kg, jaw opening of 813 mm and jaw depth of 722 mm, with a reach of 2,565 mm. Minimum excavator boom mount is 14 tonnes, and stick mount is 20 tonnes. The Model FS45R shea
  • Montabert revives popular 501 breaker name
    January 6, 2017
    Montabert has updated its most well-known hydraulic breaker. When the French company started making hammers 40 years ago, its first breaker was called the BRH501. Now Montabert is launching a new series of breakers and the first model is called the 501 Next Generation. Weighing in at 730kg, the breaker has the same power as Montabert’s previous 1,000kg models. This increase in power to weight will allow demolition contractors to use the breaker on longer reach machines, or on smaller excavators if required.
  • Montabert revives popular 501 breaker name
    April 22, 2013
    Montabert has updated its most well-known hydraulic breaker. When the French company started making hammers 40 years ago, its first breaker was called the BRH501. Now Montabert is launching a new series of breakers and the first model is called the 501 Next Generation. Weighing in at 730kg, the breaker has the same power as Montabert’s previous 1,000kg models. This increase in power to weight will allow demolition contractors to use the breaker on longer reach machines, or on smaller excavators if required.
  • VIDEO: US bridge removed with explosive demolition
    September 28, 2015
    A defunct bridge has been removed in the US State of Louisiana using explosive demolition techniques. The OK Allen Bridge was removed at the weekend, following a planned blast carried out by a demolition specialist. The bridge psanned the Red River for 79 years, providing a connection between Alexandria and Pineville. Traffic was halted on the Curtis-Coleman Bridge, which carries US 71, for safety during the demolition. The steelwork of the old bridge will be removed from the river and sold for scrap, although its concrete piers still have to be demolished.