Challenging bridge demolition

DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • Canadian air
    February 8, 2012
    Compressors from Atlas Copco are proving highly useful in highly diverse applications, on a bridge project and a quarry in Canada. Water ingress over 30 years has damaged a road bridge in Quebec City, Canada, deteriorating the concrete and breaking down the rubber expansion joints at both ends of the 150m long structure. City highway authority, Transportes Quebec, awarded local contracting company Inter-Structures the contract to replace the deteriorated concrete and fit new membrane seals. The bridge, clos
  • Auckland Harbour bridge celebrates 50 years
    February 22, 2012
    The bridge over Auckland Harbour celebrates its half century this year, and it has been given a major upgrade to ensure that safety is maintained in New Zealand's largest city. Mary Searle reports. Auckland is New Zealand's largest city, home to nearly a third of the entire country's population. It's a sprawling metropolis, and its 1.3 million people are spread over 637km² of city, suburbs and islands. The Auckland Harbour Bridge, which celebrates its 50th birthday in May, is a vital link in the city's road
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.
  • Kieswerk Kohler solves fines problem with M2500 from CDE
    September 26, 2013
    Following installation of the M2500 mobile washing plant, Kieswerk Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by CDE has also enabled the production of an additional sand product which the company is now able to offer customers. The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening proce