Challenging bridge demolition

DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • Atlas Copco changing corporate structure
    April 17, 2018
    Atlas Copco changed its corporate structure at the start of this year. Its Hydraulic Attachment Tools division will become part of Epiroc, pending shareholder approval this year. Atlas Copco will become two separate global groups of companies. Atlas Copco will focus on industrial customers while Epiroc will concentrate on mining, infrastructure and natural resources equipment. The hydraulic attachment tools division manufactures excavator attachment tools such as hydraulic breakers, cutters, pulverisers,
  • New crushing and screening developments abounded at Hillhead
    October 3, 2014
    A wide array of crushing, screening and materials handling technologies have been introduced in recent months - Mike Woof writes The manufacturers of crushing and screening products have been developing an array of new systems to optimise production. The recent Hillhead show in the UK was the launch point for a number of these new products, although firms from all over the world have also been developing new designs. Productivity and wear life are two performance factors seeing major benefits from innovatio
  • VIDEO: Saskatoon bridge demolition removes final span
    November 18, 2016
    The final section of a defunct bridge in Saskatoon has now been removed by demolition contractor Rakowski Cartage & Wrecking. Excavators fitted with hydraulic breakers were employed by the firm to break up the final span, which collapsed into the river as planned. Demolition work to remove the defunct structure commenced in 2012. Other sections of the bridge were removed using explosive demolition earlier this year.
  • New bridge over Nile will help landlocked Uganda
    April 3, 2013
    A new River Nile bridge is essential to boost trade and improve traffic in landlocked Uganda. Shem Oirere reports A new bridge across the River Nile at Jinja, to be constructed by Uganda, is promising to boost trade in eastern Africa and pave the way for smooth and safe traffic in and out of this landlocked country. The bridge, also known as the Second Nile Bridge, is the first cable-stayed bridge in the region and will be constructed at Njeru, 80km east of the Ugandan capital Kampala, along the Kampala-Jin