Challenging bridge demolition

DEMOLITION and blasting experts Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100. The efficient interaction of Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn dow
March 2, 2012 Read time: 2 mins
DEMOLITION and blasting experts 1215 Philipp Halter of Berlin, Germany, faced a challenging job: in just 48 hours it had to demolish the southern section of the Spandau Dam Bridge crossing the A 100.

The efficient interaction of 161 Atlas Copco hydraulic breakers and hydraulic CombiCutters, mounted on seven 2394 Volvo excavators, is said to have played a crucial role after following a carefully planned schedule. During Friday night a bed of sand was placed under the bridge to allow the girders and reinforcements torn down by the Atlas Copco CombiCutters to be safely collected
and transported.
 
Three 283 MB 1700 hydraulic breakers (each weighing 1,700kg and suitable for carriers in the 19-32tonne weight class) began with preparations on the bridge foundations. An SB 302 was used for the less demanding preparatory and finishing work, such as in narrow places. The light hydraulic breaker weighs 304kg and is suitable for carriers in the 4.5-9tonne weight class.

The main part of the work was handled by two Atlas Copco hydraulic CombiCutters (a CC 1700 U and a CC 2500 U) equipped with 'Universal' jaws, which crushed the concrete and cut the strong rebar of the bridge in one go. The cutters weigh 1,680kg and 2640kg, respectively. The roadblocks were removed at 5am on Monday, according to schedule, making way for one of the most significant roadwork projects in the capital on the banks of the River Spree.

For more information on companies in this article

Related Content

  • D&A Heavy Industries launch quartet of breakers at INTERMAT 2015
    April 23, 2015
    Korean company D&A Heavy Industries has unveiled four new hydraulic breakers at INTERMAT 2015. The models – D&A 650V, D&A 700V, D&A 750V, and D&A 1200V - range from 10-22tonnes in operating weight and are for excavator sizes 45-80tonnes, 58-100tonnes, 60-100tonnes, and 85-140tonnes respectively.
  • Riga's newest bridge improved traffic flow
    April 11, 2012
    An alliance of companies has come together to realise major infrastructure projects in Latvia including its biggest bridge. Patrick Smith reports. Riga, the Latvian capital, has the finest collection of Art Nouveau buildings in Europe and its centre is on the UNESCO World Heritage List.
  • Riga's newest bridge improved traffic flow
    May 9, 2012
    An alliance of companies has come together to realise major infrastructure projects in Latvia including its biggest bridge. Patrick Smith reports. Riga, the Latvian capital, has the finest collection of Art Nouveau buildings in Europe and its centre is on the UNESCO World Heritage List. The city of some 750,000 people (the country's total population is 2.2 million) is bounded to the south by Lithuania and to the north by Estonia, and is the second largest in Baltic States. To the east is Russia and Belarus.
  • Bridge lift in Orlando for interstate rebuild
    July 4, 2019
    Measuring 33.8km long and costing US$2.3 billion, Orlando’s massive I-4 Ultimate is the largest infrastructure project in the Florida Department of Transportation’s history. Divided into four phases, the project requires major bridge work to improve traffic flow through Central Florida. In all, 13 existing structures are being widened, 53 new bridges added and 74 bridges replaced. Area 2, currently under construction, runs through Orlando from Highway 50 at the northern edge to the Highway 423/I-4 interc