Skip to main content

Slovakia tunnel excavation complete

Excavation work on Slovakia’s Visnove Tunnel has now been completed. Driving the tunnel took nine months longer than originally anticipated. The 7.5km tunnel will be Europe’s seventh longest when complete and forms part of the D1 highway between Dubna Skala and Lietavska. Work on this highway started in 2014, with the construction being carried out jointly by Italian contractor Salini Impregilo and local firm Duha. Fitting out of the tunnel is now commencing, with equipment such as ventilation and traffic
September 21, 2018 Read time: 1 min

Excavation work on Slovakia’s Visnove Tunnel has now been completed. Driving the tunnel took nine months longer than originally anticipated. The 7.5km tunnel will be Europe’s seventh longest when complete and forms part of the D1 highway between Dubna Skala and Lietavska. Work on this highway started in 2014, with the construction being carried out jointly by Italian contractor 7809 Salini Impregilo and local firm Duha. Fitting out of the tunnel is now commencing, with equipment such as ventilation and traffic control systems being installed. The stretch of the D1 from Dubna Skala to Lietavska is costing €500 million to build.

For more information on companies in this article

Related Content

  • Salini Impregilo expands in the US with purchase of Lane Industries
    November 12, 2015
    Italian global infrastructure group Salini Impregilo has agreed to buy 100% of Lane Industries, an American highways contractor and the “top private asphalt producer” in the US. Lane, a family-owned business based in Cheshire, Connecticut, was bought for US$406 million and has a turnover of around $1.5 billion. The company has three divisions: asphalt production, road projects and other infrastructure projects, in domestic and international markets. A statement from Salini said Lane is participating i
  • Breakthrough on Slovakia’s D1 tunnel near Zilina
    December 12, 2016
    Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project. Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper. Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. Juraj Valent, head of the Na
  • Astaldi begins drilling tunnels on Poland’s S7 dual carriageway
    March 14, 2017
    Italian contractor Astaldi has begun drilling two parallel tunnels as part of its S7 dual carriageway project in Poland. Each tunnel, between Naprawa and Skomielna Biala and under the Lubon Maly massif, will each be just over 2km long. Astaldi, based in Rome, won the three-year S7 dual carriageway project worth around €225 million in 2016 Work includes 38 bridges and viaducts and three motorway services. There will also be 25km of access roads and two junctions. The north-south S7, when complete
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t