Equipment from XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China. The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete. The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the reg
October 15, 2018 Read time: 2 mins
Roadheaders from XCMG carried out the tunnel excavation work
Equipment from 2490 XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China.


The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete.

The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the region. Now that the 13.8km long Micang Mountain Tunnel is complete, there is a direct route that will cut journey times substantially.

Now that the project is complete, this is the third longest road tunnel in the world, and the longest in China. The tunnel on the Sichuan-Shaanxi Expressway will slash the travel time for travelling around the Micang Mountain from four hours to just 30 minutes now that drivers can go directly underneath.

Inaccessibility of the site provided the biggest challenge to the construction workers as the construction work was carried out in an area that was difficult to access. However, there were many other challenges also including tropical rain, highly stressed rock conditions and high concentrations of dangerous gases.

The rare brittle rock mass in the high geostress area that the Micang Mountain Tunnel traverses has a high risk of rock bursts, landslides, fractures, cracks and even cave-ins. To maximise safety, this required real-time monitoring of the rock conditions throughout the construction operation. In addition, toxic gases released during tunnel excavation operations required workers to wear safety gear, adding to discomfort for personnel.


In order to overcome these difficulties and speed the construction work, mechanised cutting was selected as the main tunnelling method at the start of the project. XCMG’s Railway Equipment Division sent its two triple boom drilling jumbos to the project contractor: First Project Department under China Railway Engineering Group to assist in the tunneling operation. XCMG also supplied the mechanised cutting equipment that carried out the majority of the tunnel driving work. Both the drill jumbo and the roadheader machines performed reliably, despite the tough conditions, helping to ensure that the work was completed successfully.

For more information on companies in this article

Related Content

  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Mexico’s new highway for Oaxaca
    May 3, 2023
    Mexico’s Oaxaca State is to benefit from a major new highway link – Mauro Nogarin and Mike Woof report
  • Colombia’s Toyo Tunnel project providing key link
    May 20, 2016
    Colombia’s Toyo Tunnel project will provide an important new link for the country, writes Mauro Nogarin. The new Toyo Tunnel project is of immense importance for Colombia, improving transportation and providing an important road link. The work is being carried out by the Antioquia to the Sea Consortium, which comprises of FCC Construction, Cass Builders and Company, Carlos Alberto Solarte and Estyma Studies and Handling. These firms are building the Toyo Tunnel project and the various access roads, with the
  • Improving tunneling method selection
    December 11, 2015
    The tunnelling sector remains one of the most active segments of the construction industry worldwide, fuelling demand for equipment However, there have been issues with the efficiency of the selection process for the most suitable tunnelling method for a project in the past. With this in mind, the Italian hydraulic breaker manufacturer Indeco has been working on a new algorithm that allows a contractor to optimise the tunnelling method selection. The firm said that this system has been developed becau