Tunnelling project under Micang Mountain

Equipment from XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China. The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete. The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the reg
October 15, 2018 Read time: 2 mins
Roadheaders from XCMG carried out the tunnel excavation work
Equipment from 2490 XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China.


The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete.

The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the region. Now that the 13.8km long Micang Mountain Tunnel is complete, there is a direct route that will cut journey times substantially.

Now that the project is complete, this is the third longest road tunnel in the world, and the longest in China. The tunnel on the Sichuan-Shaanxi Expressway will slash the travel time for travelling around the Micang Mountain from four hours to just 30 minutes now that drivers can go directly underneath.

Inaccessibility of the site provided the biggest challenge to the construction workers as the construction work was carried out in an area that was difficult to access. However, there were many other challenges also including tropical rain, highly stressed rock conditions and high concentrations of dangerous gases.

The rare brittle rock mass in the high geostress area that the Micang Mountain Tunnel traverses has a high risk of rock bursts, landslides, fractures, cracks and even cave-ins. To maximise safety, this required real-time monitoring of the rock conditions throughout the construction operation. In addition, toxic gases released during tunnel excavation operations required workers to wear safety gear, adding to discomfort for personnel.


In order to overcome these difficulties and speed the construction work, mechanised cutting was selected as the main tunnelling method at the start of the project. XCMG’s Railway Equipment Division sent its two triple boom drilling jumbos to the project contractor: First Project Department under China Railway Engineering Group to assist in the tunneling operation. XCMG also supplied the mechanised cutting equipment that carried out the majority of the tunnel driving work. Both the drill jumbo and the roadheader machines performed reliably, despite the tough conditions, helping to ensure that the work was completed successfully.

For more information on companies in this article

Related Content

  • Chile-Argentina Agua Negra Tunnel progress
    February 16, 2018
    The names of the contractors offering bids for the new Agua Negra Tunnel project connecting Chile and Argentina will be revealed in March 2018. Several firms have already expressed a keen interest in this major engineering project. Contractors that have expressed interest include CRS, a consortium comprising China Railway Tunnel Group and Benito Roggio e Hijos. In addition, Ingenieria y Construccion Sigdo Koppers and OHL are also interested in the project as are the firms Rovella and Condotte. The project
  • Let’s Boogie in a new tunnel
    July 7, 2020
    The new Victory Boogie Woogie Tunnel will be the most sustainable tunnel in the Netherlands.
  • Record size TBM supplied for Chinese tunnel project
    June 7, 2024
    A record sized TBM is being supplied for a Chinese road tunnel project.
  • Increasing importance of alternate truck routes
    February 14, 2012
    The fabled Silk Route from China to Europe takes many forms, and is again becoming increasingly important as Patrick Smithreports The ancient Silk Road was never a single caravan route, but covered hundreds of kilometres in width extending in length for around 10,000km. This is the view of the European International Road Transport Union (IRU), and many other countries and organisations, who point out that it is a system of routes covering many countries via a series of branch roads that dates back some 2