Transylvanian motorway breaks new ground in engineering

Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."
July 11, 2012 Read time: 4 mins
Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."

Bogdan was speaking about the Cluj-Napoca section of the Transylvanian Motorway, a massive 415km, four-lane highway featuring more than 300 bridges, 70 overpasses and 19 interchanges. It is the largest highway project in Europe. When complete in 2013, it will connect central Romania with the country's northwestern border with Hungary. And it will make what is now a tough ten-hour tour into a smooth three-hour breeze.

This sleek new €2.2 billon (US$3 billion) national highway will bring the country's infrastructure in line with that of its new economic partners. The road will ease traffic jams, improve safety, and open up the country to new possibilities for tourism and trade, likely becoming the preferred route between the Black Sea and Western Europe.

4138 Bechtel and 5252 Enka, two leading construction companies, are handling the project together. They brought an existing fleet of 67 178 Caterpillar machines and purchased an additional 68 especially for this project. Now, across the valleys, mountains and plains of Transylvania you can see Cat excavators, dozers, wheel loaders, dump trucks, motor graders, soil compactors, cold planers, wheel pavers and generators.

As part of its regular service to all its customers, local Cat dealer, 2154 Bergerat Monnoyeur, ensures a secure and fast supply of original Cat spare parts and consumables. It also provides a full day's training on-site by an experienced service technician, with every machine's delivery. "Our technicians ensure that the customers' operators know all about the daily inspection and routine servicing," says Mihai Hotinceanu of Bergerat Monnoyeur. "They also give some advanced operator training to help ensure maximum productivity and efficient machine use. "Of course, we cannot train all the operators so we describe these one-day visits as 'train-the-trainer' sessions, the knowledge trickles down to all operators on the job site."


The road to prosperity

Road building is always good news for the local economy: it immediately creates new jobs and new skills in the project itself as well as driving demand for supporting products and services throughout the nation. But the sheer scale of this project represents a massive injection of energy into the Romanian economy. Currently, more than 3,000 Romanians (93% of the project team) are working on the motorway, and in 2010, at the peak of construction, that number will exceed 8,000.

When the road fully opens in 2013, it will be a powerhouse for Romania's economic development as it will open trade routes from central Romania to its European and Central Asian neighbours. In addition, the country is already gearing up for an expected 30% increase in tourism and many analysts predict that collateral investments will equal that of the motorway's €2.2 billon.

Bridge to the past and the future

Romania is a country with a rich history: not only was the region intensely colonised by the ancient Romans (hence the name: Romania), its history of civilisation stretches many millennia. In fact the oldest modern human remains in Europe were discovered here six years ago. Not surprisingly then, on a jobsite that spans 3,320 hectares the road builders have unearthed some rather special sites of historical interest. So far, 14 archaeological teams have retrieved hundreds of artefacts, and digs around Cluj revealed a 6,500-year-old settlement with huts and coloured pottery. "It's good to remember the past," says Bogdan of Bechtel. "But it's also good to think of the future, and we hope what we're building here will provide progress and prosperity for many years to come."

Preparing the rural communities: School children, herdsmen and other locals are currently receiving road safety awareness training. This is backed up with free reflective bands on school satchels and horse-drawn wagons. The new motorway will pass through rural regions where the local communities live an uncomplicated life. That's why Bechtel and Enka are preparing the locals for the eventual arrival of large amounts of fast-moving traffic. The team has partnered with local traffic authorities on road safety training, and every project driver has taken defensive driving classes. So far, more than 800 Romanian children have learned theoretical and practical lessons in road safety, and 1,000 herdsmen and shepherds have been given reflective vests free-of-charge. Safety crews have even fitted out 100 horses with reflective collars.

For more information on companies in this article

Related Content

  • Thailand's school zones project wins Evonik award
    March 13, 2017
    The Department of Rural Roads, Thailand (DRR) was rewarded for a comprehensive road safety initiative around schools, especially in rural areas. The award ceremony was held in the IRF offices in Geneva According to the World Health Organisation (WHO), Thailand ranks among the countries with the highest number of traffic fatalities/ capita. In 2015, the country saw a road death rate of 36.2/100,000 of population. With this, Thailand ranked second in fatal traffic crashes worldwide and its situation regard
  • Kosovan highway ahead of schedule
    April 25, 2012
    In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
  • Bechtel and Enka complete further Kosovan motorway stretch
    July 13, 2012
    Bechtel and its joint venture partner, Enka, have completed a further 4.5km of the Kosovo motorway. The new section, which takes the total completed by Bechtel and Enka to 42.5km, opened on Friday 13 July and connects with the stretch of motorway delivered in November 2011 going from Morinë at the border with Albania to Suhareka. The growing Kosovo motorway now extends to the Dule interchange in Northern Kosovo. The latest stretch was built in less than a year, ahead of schedule and within budget.
  • Transforming Algeria's road network
    February 9, 2012
    Highway construction work is transforming Algeria, providing the country with a new network of highway quality road connections.