New Doha highway under construction

Construction is now underway on the New Orbital Highway in Doha, Qatar. This project is called The New Orbital Highway contract 2 and is one of the largest projects being delivered through the Qatar’s public work authority Ashghal. The work consists of the design and construction of 47km of highway with a five-lane dual carriageway for light vehicles and two truck lanes in each direction. It also includes six viaducts, 17 bridges and underpasses and a 320m cut-and-cover tunnel. This last is particularly
March 18, 2016 Read time: 3 mins
The cutter drum is centrally mounted and extends past the machine’s tracks
Construction is now underway on the New Orbital Highway in Doha, Qatar. This project is called The New Orbital Highway contract 2 and is one of the largest projects being delivered through the Qatar’s public work authority Ashghal.

The work consists of the design and construction of 47km of highway with a five-lane dual carriageway for light vehicles and two truck lanes in each direction. It also includes six viaducts, 17 bridges and underpasses and a 320m cut-and-cover tunnel. This last is particularly complex and includes eight grade-separate interchanges with cross roads, collectors-distributors, overpass and underpass structures, pedestrian and bicycle paths and landscaping. Major infrastructure improvements will be built as part of the project, including a new and efficient storm water drainage network, as well as treated sewage effluent networks, electrical and telecommunication networks, street lighting and substations

The joint venture firm QDVC-Bin Omran is handling the US$1.6 billion contract and the work started in May 2014 while it is due for completion within 36 months.

QDVC is a Qatari company comprising local firm 3438 Qatari Diar Real Estate Investment Company and French firm 3085 VINCI Construction Grands Projets. The relationship between 2342 Tesmec and QDVC started in September 2013, when QDVC used its first Tesmec machine (Tesmec model 1475 RH) for the construction of one of Doha’s subway stations.

QDVC was convinced with the quality of the machine and the level of service provided by the local Tesmec team. As a result, QDVC then opted to purchase three Tesmec 1475 RHs for its new project: the New Orbital Highway (NOH2). Subsequently, six more units have been purchased to increase QDVC’s Tesmec fleet to nine machines. All nine are currently excavating and levelling along the 47km route.
The units purchased by QDVC are eight Tesmec model 1475 RH (Rock Hawg) and one Tesmec model 1475 CS (chainsaw). The 1475 RH is a 110tonner powered by a C18 178 Caterpillar diesel delivering 470kW. The machine’s drum allows it to extract rock 3.81m wide and to a depth of 600mm.

This machine can be used to excavate rock in the conditions cost-effectively and productively, without the need for the use of explosives. Compared with blasting, mechanised cutting is a safe working method as the risk of flyrock is much reduced. From an environmental perspective any dust produced is localised (and can be controlled using water if required). Meanwhile the noise levels are low and continuous and there are no shock waves generated that can cause damage to buildings in the vicinity of the working area, so the machine can be used in urban areas with minimal disturbance.

Compared to other mechanical excavation methods (such as excavators with hydraulic rock breakers) the machine is said to be highly cost-effective. The equipment is said to be up to 15 times more productive in this type of application than a 25tonne class excavator fitted with rock cutting equipment.

The material produced by the cutting process is also uniform in size, making it easier to handle than the blasted rock produced when drilling and blasting. The cuttings are also suitable for use in backfilling or for road base applications, reducing costs with regard to buying or transporting materials to site.

Another benefit of the Rock Hawg is that the unit can be used to excavate vertical sidewalls due to the drum being wider than the machine’s own tracks. With the drum being centrally supported, the machine is also able to excavate rock with square corners so that the surface may not require any additional finishing.

For more information on companies in this article

Related Content

  • Asphalt plant innovations
    June 14, 2019
    New developments in asphalt plant technology are offering better cost efficiency and materials quality for the industry
  • Bridges and roads part of Myanmar’s New Yangon development
    April 6, 2018
    At least two bridges and dozens of kilometres of roads are part of phase one of an ambitious Myanmar plan to build a new city. Other infrastructure projects are an industrial zone, a power plant and water and sewage treatment plants, according to the newly created overseeing body, New Yangon Development Corporation - NYDC. The new city will cover around 30,000 acres on the west side of the Yangon River, including land in Kyimyindaing, Seikgyikanaungto and Twante townships. Much of the work to create the
  • Intermat Middle East positions itself for growth
    October 17, 2012
    As the United Arab Emirates gears up to invest more than US $4.6 billion (UAE Dirham 17 billion) in its nationwide road network in the next few years, the second annual INTERMAT Middle East show has taken place in Abu Dhabi with suppliers like AAA Cranes, Miller UK, Kanoo, Liebherr, Sennebogen, WireCo World, Erkat, Terex Finlay, Atlas Copco, , ELSA SRL, Robit Rock Tools, Ramtec Robi, Scheuerle Fahrzeugfabrik, T.G.S – The Grab Specialist, BV Beco, Techking Tires, Blastrac, SK Solutions, Xcentric Internationa
  • Success of hot mix asphalt road recycling
    March 7, 2012
    Russian construction firm Kamdorstroy has carried out a successful demonstration of recycling techniques to over 60 highway officials, academics and contractors from all over the CIS states. The demonstration was carried out in co-operation with the Russian Federal Highway and Tatarstan Highway authorities and involved milling, recycling and overlaying a road with hot mix asphalt. The work was carried out on a 7.5m wide roadway with 3.8m wide lanes (with an overlap) using machinery and techniques new to Rus