Drilling rig meets the utility supply challenge

A tricky utility supply project has been carried out in difficult conditions in Germany, without disturbing a village access road. The drilling work for the project was operated by boring contractor Beermann and the site was located on a plateau some 5km from the nearest village.
April 11, 2012 Read time: 3 mins
Using a powerful rig from Tracto- Technik, German contractor Beermann has managed to complete a steeply sloping utility installation under a village access road

A tricky utility supply project has been carried out in difficult conditions in Germany, without disturbing a village access road. The drilling work for the project was operated by boring contractor Beermann and the site was located on a plateau some 5km from the nearest village.

The forest lane leading to the working area was only accessible with 4-wheeldrive vehicles over its final 300m and it took one working day to setup the equipment at the jobsite. Water to mix the drilling fluid for the bore was extracted from the Wipper River some 6km away and was transported to the jobsite in 10m³ tanks hauled by tractors. The work was needed to replace an old gas pipe over a 2km length to the town of Sollstedt and the HDD rig chosen to install the new bore was a Type 25N Grundodrill built by 2738 Tracto-Technik.

The distance between the HDD rig and the start of the steep slope was approximately 70m and this made an entrance angle of about 42% necessary to be able to meet the planned bore exit point at the foot of the steep slope. In comparison to most projects where the bore entrance angle is usually at 10-24%, the bore angle was very acute and required careful working.

The ground conditions on the bore path comprised layers of weathered and very solid limestone and the pilot bore had to take into account these ground conditions. An aggressive boring head with special hard metal bore tips was used while a depth sonde from specialist DCI was fitted for the monitoring and steering. The cover on the steep slope was almost 25m deep in parts, which resulted in the signal being marginal at times. However, the signal got stronger after the critical phase of the bore confirming that the contractor was on course and the pilot bore was completed on target. Two pilot bore expansion bores, with 250mm and 350mm diameter reamers, followed with the runs taking just 5 minutes per drill rod length to pull through. The drilling fluid was collected at the target point and passed on to a second deeper pit at the access road and then disposed of by a suction/vacuum transporter. After each expansion bore the backreamer was pushed back through the bore hole in order to compress and rinse out the bore spoils to prevent the product pipe getting stuck when it was finally pulled in. After the final cleaning process the bore was cleaned thoroughly and made ready for installing of the product pipe.

Some 12 steel 200mm diameter pipes with a PE and reinforced fibre glass coating were welded together, x-rayed and checked for tightness with water at 100bars. Then the PE and reinforced fibre glass coating was reinstated at the welding point. Installed along with the gas pipe were four HDPE pipes of 50mm diameter and 4.6mm wall thickness which were pulled in to host the control cable and also for the filling of the annular space.

A Bagela cable winch pulled the pipe string uphill to the bore hole and the pipe installation process began as soon as the final backreamer had been connected. The weight of the pipe string was calculated to be 5.7tonnes, while the tensile load was an average of 9tonnes and well below the rig's reserve load of 25tonnes. From the bore exit point, the pipeline installation used the open trench method and a milling cutter had already excavated a 1.3m deep trench.

For more information on companies in this article

Related Content

  • Geosynthetic solution for ground preparation
    April 16, 2012
    Naue Geosynthetics says its Secugrid offers a solution for a host of ground preparation problems, and for use in reinforced retaining walls. Secugrid is a geogrid made from extruded monolithic flat bars with welded junctions, for soil reinforcement in earth, landfill and road construction as well as in hydraulic engineering applications. Among its benefits are said to be its high strength and low elongation thanks to the extruded elements. "The monolithic flat bars give it a robust construction, an
  • Major Necaxa-Tihuatlan Highway project for Mexico
    October 1, 2014
    A new highway in Mexico is connecting Necaxa with Tihuatlan and the project features challenging terrain - Mauro Nogarin reports In Mexico a landmark highway project is now close to completion, having set a number of records for Latin America.
  • Norway’s record breaking undersea road tunnel
    February 25, 2015
    The world's deepest road tunnel is currently in construction near Stavanger in Norway but is only the prelude to even larger projects - report and photographs by Adrian Greeman. Norway's convoluted coastline of fjords and high mountains is famously scenic but also a major problem for transport and connections. The country has long experience of constructing tunnels as a result. Now a series of tunnels underway, or in design, around the oil industry city of Stavanger will stretch its skills more than usual.
  • Improving a key route through Florida
    November 9, 2015
    Upgrading a key route through Florida – novel construction techniques are helping widen a road in difficult geological conditions – Lucio Garofalo reports. A major road widening project underway in Florida is due for completion soon. The work will improve an important section of road, reducing congestion at peak period and cutting travel times for drivers. The US 331/SR83 highway runs for some 79km and provides an important link in Florida’s Panhandle area, as it connects with Route 98.