M27 gets ESS bases from Marshalls Civils

Precast bases for electronic signalling systems help convert the UK's M27 into a smart motorway.
By David Arminas August 30, 2021 Read time: 2 mins
Precast foundations by Marshalls Civils & Drainage speed up the upgrade of the M27

Marshalls Civils and Drainage has been installing its precast concrete bases for electronic signalling systems along England’s M27 as part of a smart motorway conversion.

The £244 million (US$338 million) motorway conversion by Highways England runs for 24km.

Between junctions 9 and 11, nine of the 2.3m x 1.6m x 1m deep concrete units have been installed by main contractor J McCann. The units along the will act as foundations for new slip road entry and stop signals to make the former hard shoulder a permanent running lane.

Marshalls says that the ESS installation was done by using MMC - Modern Methods of Construction – and was completed more quickly than would have been using the older cast-in-situ bases. This also eliminated the weather risk from planning the manufacture and installation. Between two and three of the units per night were lifted by crane into pre-prepared excavations then backfilled with self-impacting gravel.

The base units were manufactured with a bitumen coating at Marshalls’ production site in Mells, county Somerset, and are now being considered by McCann’s as standard use for electronic signalling systems. Marshalls is also hoping to supply 1200mm x 1200mm CCTV bases to McCann’s for the smart motorway conversion of the M6 motorway between junctions 21 and 26.

Bart Maslon, project supervisor with McCann, said the units were made-to -order because they had to be larger than usual. Being able to install up to four foundations per night would not be achievable if the foundations were cast on site. “Offsite is definitely the way forward. The Marshalls bases were manufactured, delivered and installed exactly as planned and programmed.”

For more information on companies in this article

Related Content

  • Importance of road/tunnel drainage systems
    May 8, 2012
    A variety of systems are available for quickly and efficiently removing water from roads as Patrick Smith reports. The presence of water in a highway layer reduces the bearing capacity of the road, and in doing so it also reduces the structure's lifetime. Indeed, the recent extremely cold winter in many parts of Europe has shown that in colder climates there is a risk of frost damage when water is present resulting in costly potholes, so drainage systems performing properly are important in road design.
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
  • Drilling rig meets the utility supply challenge
    April 11, 2012
    A tricky utility supply project has been carried out in difficult conditions in Germany, without disturbing a village access road. The drilling work for the project was operated by boring contractor Beermann and the site was located on a plateau some 5km from the nearest village.
  • Drilling rig meets the utility supply challenge
    May 9, 2012
    A tricky utility supply project has been carried out in difficult conditions in Germany, without disturbing a village access road. The drilling work for the project was operated by boring contractor Beermann and the site was located on a plateau some 5km from the nearest village.