Work to start on Tyne Bridge refurbishment

In the UK, Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs.
By David Arminas March 11, 2024 Read time: 2 mins
Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge (image © David Shaun Dodds/Dreamstime)

Work will start April 2 on refurbishing the Tyne Bridge between Newcastle and Gateshead after month of waiting for €41 million of UK government funding.

Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs. Last September Scaffolding work by Infrastructure Site Services was started in preparation for ESH’s main bridge works.

Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge whose main arch span is around 162m.

The bridge over the River Tyne in north East England was designed by engineering firm Mott, Hay and Anderson which went on to design the Forth Road Bridge in Scotland.

Government funding of €41 million was confirmed in February, according to Newcastle City Council. The total €48.5 million package includes upgrade to the A167 Central Motorway in Newcastle.

A full programme will be set out in due course, detailing the phasing of the refurbishment which will see various sections of the iconic structure clad in scaffolding over the four-year period. Scheduling of the central motorway upgrade will also be confirmed in the coming weeks.

The full programme to the Tyne Bridge includes steelwork repairs, full grit blasting and re-painting, concrete repairs, drainage improvements, stonework and masonry repairs, bridge deck waterproofing and resurfacing, parapet protection and bridge joint replacement.

For more information on companies in this article

Related Content

  • UK smart motorway work for M4 link
    September 16, 2019
    Highways England in the UK is carrying out major upgrade work for the busy M4 motorway, running west from capital London. In all 11 bridges are being replaced along a 51km stretch of the M4 between London and Reading. When complete, the current hard shoulder will have been rebuilt and resurfaced to allow traffic to use it as a live lane. The section carrying the heaviest traffic, between the M25 ring road around London and the main exit for Heathrow Airport, will be widened so that it will feature five la
  • England road upgrades planned
    June 14, 2021
    A road upgrade programme is planned for the East of England.
  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b
  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.