Work to start on Tyne Bridge refurbishment

In the UK, Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs.
By David Arminas March 11, 2024 Read time: 2 mins
Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge (image © David Shaun Dodds/Dreamstime)

Work will start April 2 on refurbishing the Tyne Bridge between Newcastle and Gateshead after month of waiting for €41 million of UK government funding.

Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs. Last September Scaffolding work by Infrastructure Site Services was started in preparation for ESH’s main bridge works.

Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge whose main arch span is around 162m.

The bridge over the River Tyne in north East England was designed by engineering firm Mott, Hay and Anderson which went on to design the Forth Road Bridge in Scotland.

Government funding of €41 million was confirmed in February, according to Newcastle City Council. The total €48.5 million package includes upgrade to the A167 Central Motorway in Newcastle.

A full programme will be set out in due course, detailing the phasing of the refurbishment which will see various sections of the iconic structure clad in scaffolding over the four-year period. Scheduling of the central motorway upgrade will also be confirmed in the coming weeks.

The full programme to the Tyne Bridge includes steelwork repairs, full grit blasting and re-painting, concrete repairs, drainage improvements, stonework and masonry repairs, bridge deck waterproofing and resurfacing, parapet protection and bridge joint replacement.

For more information on companies in this article

Related Content

  • Warwick junction upgrade in the UK
    December 7, 2020
    The A46 Stoneleigh Junction in the UK is to benefit from a major upgrade.
  • Call for action on road markings
    April 11, 2012
    In Staffordshire, in the West Midlands region of England, some residents are reported to be so fed-up of waiting for traffic lines to be painted on roads by the local county council that they are threatening to do it themselves. Staffordshire County Council highways bosses say they can only take on four new traffic measure projects a year and have a waiting list stretching to 2028. Media outlets in the county report that the local authority currently has more than 70 requests from all over Stafford borough
  • Innovative new drainage solutions will help keep roads free from water
    October 2, 2014
    An array of new technologies will help optimise road drainage and minimise flooding risks - Mike Woof reports In the UK the specialist contractor Lanes Group has carried out extensive inspection work of the drainage systems for the M6 toll route around the city of Birmingham. A powerful zoom camera has been used to carry out the inspection work for Midland Expressway, which operates and maintains the 43km-long motorway, running from Coleshill to Cannock.
  • Video: North Tyneside’s triple decker Silverlink on schedule
    August 29, 2018
    Highways England reports that the Silverlink triple-deck roundabout in North Tyneside is 80% complete and on schedule for opening in March next year. The €83 million project involves lowering the A19 highway underneath the Silverlink roundabout and A1058 Coast Road. The new road is expected to be used by 35,400 vehicles daily. “We are now entering the final stages,” said Steven Cox, Highways England assistant project manager. “Work to remove the 80,000m³ of soil has now been completed [and] we have six m