Work to start on Tyne Bridge refurbishment

In the UK, Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs.
By David Arminas March 11, 2024 Read time: 2 mins
Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge (image © David Shaun Dodds/Dreamstime)

Work will start April 2 on refurbishing the Tyne Bridge between Newcastle and Gateshead after month of waiting for €41 million of UK government funding.

Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs. Last September Scaffolding work by Infrastructure Site Services was started in preparation for ESH’s main bridge works.

Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge whose main arch span is around 162m.

The bridge over the River Tyne in north East England was designed by engineering firm Mott, Hay and Anderson which went on to design the Forth Road Bridge in Scotland.

Government funding of €41 million was confirmed in February, according to Newcastle City Council. The total €48.5 million package includes upgrade to the A167 Central Motorway in Newcastle.

A full programme will be set out in due course, detailing the phasing of the refurbishment which will see various sections of the iconic structure clad in scaffolding over the four-year period. Scheduling of the central motorway upgrade will also be confirmed in the coming weeks.

The full programme to the Tyne Bridge includes steelwork repairs, full grit blasting and re-painting, concrete repairs, drainage improvements, stonework and masonry repairs, bridge deck waterproofing and resurfacing, parapet protection and bridge joint replacement.

For more information on companies in this article

Related Content

  • 'Tricky' bridge project
    February 7, 2012
    Contractor Ringway has completed work on a tricky project to replace Stile Farm Bridge, which crosses the Great Stour River near Chilham in County Kent, south-east England. Built in the 1920s, the bridge was in a severe state of disrepair resulting in weight restrictions of just 3tonnes. The new structure has a 16m span and is constructed using pre-cast concrete, with pre-stressed steel-reinforced beams based on cast in-situ abutment, and enables the bridge to carry heavier traffic. As well as helping to ea
  • Spencer Group cable access for Pattullo Bridge
    July 3, 2023
    Spencer is working on behalf of Fraser Crossing Constructors GP - a joint venture between Acciona and Aecon - on the suspension bridge near Vancouver, Canada.
  • Balfour and Vinci slide bridge over the M42
    January 6, 2023
    Workers slid the concrete shell of a 12,600-tonne bridge a record 165m to position it across the M42 motorway in the northern English county of Warwickshire.
  • A thousand birthday greetings for US-Canada Thousand Island Bridge
    August 21, 2018
    The Canada-US Thousand Island Bridge system celebrated its 80th birthday in August with presentations and an open house at its US headquarters. The 33.7km three-bridge system over the St Lawrence River took 16 months to build and was completed 10 weeks ahead of schedule. It runs from Collins Landing near Alexandria Bay in the US state of New York to the small town of Ivy Lea in the Canadian province of Ontario. The system connects US Interstate 81 and Canada’s Highway 401, a major motorway between Montre