Work to start on Tyne Bridge refurbishment

In the UK, Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs.
By David Arminas March 11, 2024 Read time: 2 mins
Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge (image © David Shaun Dodds/Dreamstime)

Work will start April 2 on refurbishing the Tyne Bridge between Newcastle and Gateshead after month of waiting for €41 million of UK government funding.

Esh Construction was appointed by Newcastle and Gateshead councils in June 2022 to carry out the €48.5 million programme of repairs. Last September Scaffolding work by Infrastructure Site Services was started in preparation for ESH’s main bridge works.

Completion of work is expected in 2028 to mark the centenary of the 389m-long and 17m-wide through arch steel bridge whose main arch span is around 162m.

The bridge over the River Tyne in north East England was designed by engineering firm Mott, Hay and Anderson which went on to design the Forth Road Bridge in Scotland.

Government funding of €41 million was confirmed in February, according to Newcastle City Council. The total €48.5 million package includes upgrade to the A167 Central Motorway in Newcastle.

A full programme will be set out in due course, detailing the phasing of the refurbishment which will see various sections of the iconic structure clad in scaffolding over the four-year period. Scheduling of the central motorway upgrade will also be confirmed in the coming weeks.

The full programme to the Tyne Bridge includes steelwork repairs, full grit blasting and re-painting, concrete repairs, drainage improvements, stonework and masonry repairs, bridge deck waterproofing and resurfacing, parapet protection and bridge joint replacement.

For more information on companies in this article

Related Content

  • First bridge deck section joined on UK’s Mersey Gateway project
    June 30, 2017
    The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)
  • Indeco cuts up New York City’s old Kosciuszko Bridge
    November 23, 2017
    An Indeco ISS 45/90 is proving essential for demolishing the old Kosciuszko Bridge in New York City. New York City’s old 1.9km Kosciuszko Bridge, which crosses Newtown Creek connecting Green Point, Brooklyn with Maspeth, Queens, has been out of service since April. By the end of the year, the polygonal Warren through-truss structure will be no more. To replace the old bridge, in 2009, the New York State Department of Transportation planned the construction of two cable-stayed replacement bridges.
  • Colorado river bridge relieves congestion
    February 7, 2012
    Built in the shadow of the Hoover Dam, a new bridge is set to takes its place as another major tourist attraction. Patrick Smith reports