UK motorway upgrade ahead of schedule

Joint venture contractor Skanska Balfour Beatty has completed work on a 19km section of the M25 motorway in the UK, six months ahead of schedule. Work on the M25 scheme between junctions 5 and 7 in Kent and Surrey forms part of a new generation of technology-driven improvements on the UK’s strategic road network.
May 1, 2014 Read time: 2 mins
M25 section 2 - operational smart motorway
Joint venture contractor 2296 Skanska 1146 Balfour Beatty has completed work on a 19km section of the M25 motorway in the UK, six months ahead of schedule. Work on the M25 scheme between junctions 5 and 7 in Kent and Surrey forms part of a new generation of technology-driven improvements on the UK’s strategic road network. These smart motorways are intended to deliver increased overall capacity, shorter journey times and reduced congestion. An overhead technology system provides drivers with optimum driving speeds to ensure that these goals are achieved. The scheme is contributing to making the busy M25 technologically advanced, with hard shoulder running and variable speed limits combining to make a permanent all-lane running smart motorway. Skanska Balfour Beatty has used Building Information Modelling (BIM) to provide real-time information to the construction teams and allow improvements to the design, reducing the need for time being spent on manual intervention. The project has utilised an electronic sign-off system which has led to a reduction in the delays incurred by previous off-line methods and also helped to save on initial project budget projections. Meanwhile over 90% of materials including fill material have come from recycled or reclaimed sources.

John Payne, 2309 Highways Agency Project Manager said, “The improvements on the M25 in Kent and Surrey are part of the £1.7 billion of investment into roads in the South East by 2021. The new smart motorway will provide extra capacity and offer more reliable journeys for the 140,000 drivers that use this stretch of road every day. I’m particularly pleased that the southern section of the M25 has opened well ahead of planned completion this winter thanks to rescheduling of the programme.”

Drivers will also benefit from the full completion of the Northern section between Junctions 23 to 27 later this year.

For more information on companies in this article

Related Content

  • UK’s A14 widening project ramps up with a recruitment drive
    November 11, 2016
    Contractors are gearing up for one of the UK’s largest road projects, the 34km widening of the A14 between the town of Huntingdon and city of Cambridge. The €1.7 billion government-funded scheme will be delivered over four years by a joint venture between Skanska, Costain, Balfour Beatty and Carillion.
  • Balfour Beatty wins road contract for Norfolk
    November 27, 2015
    Balfour Beatty has been awarded a €147.72 million (£104 million) road scheme by Norfolk County Council to complete works on the Norwich Northern Distributor Road (NNDR). The new road will serve Broadland, Norfolk, and improve access to North Norfolk and Norwich International Airport, with better links to Great Yarmouth and the south of the region. It will also bring relief on congested and unsuitable roads around the north and east of Norwich and improve capacity for future growth in jobs and housing.
  • Mott MacDonald’s motorway to motorway metering
    December 20, 2017
    Mott MacDonald has developed a Motorway to Motorway (M2M) metering pilot scheme. This has been developed for Highways England and is being trialled between junction 21A of the M6 and junction 10 of the M62. The project is intended to smooth traffic flows and reduce the number of queues that occur because of congestion.
  • Turner & Townsend picks up services deal for Stonehenge in the UK
    April 6, 2018
    Professional services company Turner & Townsend has been appointed to provide commercial services for two major Highways England programmes, including its flagship A303 Stonehenge scheme. The A303 upgrade includes plans to build a road tunnel near Stonehenge, a prehistoric monument in western England believed to have been built around 3,100 BC. The road project is part of a series of planned upgrades to A303/A358 corridor to improve connectivity between the south east and south west of England. The