UK motorway upgrade ahead of schedule

Joint venture contractor Skanska Balfour Beatty has completed work on a 19km section of the M25 motorway in the UK, six months ahead of schedule. Work on the M25 scheme between junctions 5 and 7 in Kent and Surrey forms part of a new generation of technology-driven improvements on the UK’s strategic road network.
May 1, 2014 Read time: 2 mins
M25 section 2 - operational smart motorway
Joint venture contractor 2296 Skanska 1146 Balfour Beatty has completed work on a 19km section of the M25 motorway in the UK, six months ahead of schedule. Work on the M25 scheme between junctions 5 and 7 in Kent and Surrey forms part of a new generation of technology-driven improvements on the UK’s strategic road network. These smart motorways are intended to deliver increased overall capacity, shorter journey times and reduced congestion. An overhead technology system provides drivers with optimum driving speeds to ensure that these goals are achieved. The scheme is contributing to making the busy M25 technologically advanced, with hard shoulder running and variable speed limits combining to make a permanent all-lane running smart motorway. Skanska Balfour Beatty has used Building Information Modelling (BIM) to provide real-time information to the construction teams and allow improvements to the design, reducing the need for time being spent on manual intervention. The project has utilised an electronic sign-off system which has led to a reduction in the delays incurred by previous off-line methods and also helped to save on initial project budget projections. Meanwhile over 90% of materials including fill material have come from recycled or reclaimed sources.

John Payne, 2309 Highways Agency Project Manager said, “The improvements on the M25 in Kent and Surrey are part of the £1.7 billion of investment into roads in the South East by 2021. The new smart motorway will provide extra capacity and offer more reliable journeys for the 140,000 drivers that use this stretch of road every day. I’m particularly pleased that the southern section of the M25 has opened well ahead of planned completion this winter thanks to rescheduling of the programme.”

Drivers will also benefit from the full completion of the Northern section between Junctions 23 to 27 later this year.

For more information on companies in this article

Related Content

  • SWARCO completes installation on UK’s busiest north east highways
    March 22, 2017
    SWARCO has installed a network of 27 variable message signs at some of the busiest highway locations in the northern UK’s Tyneside region. The signs give motorists key information to help them plan their journey and warn them of weather disruption and other potential hazards. Planning and coordinating all works with each local authority was the major challenge, requiring some of the installations to be made in the dead of night. The city of Newcastle was the contracting local authority acting for the Nor
  • Balfor Beatty selling Parsons Brinckerhoff to WSP Global
    September 5, 2014
    Balfour Beatty is selling its Parsons Brinckerhoff business to WSP Global for US$1.3525 billion (£820 million). Part of the agreement is that $110 million (£67 million) being retained within Parsons Brinckerhoff. With the acquisition of Parsons Brinckerhoff, WSP becomes one of the world’s largest professional services firms. The deal increases WSP’s presence across global emerging markets in Asia and Australasia as well as providing opportunities in the UK market, where Parsons Brinckerhoff is well-establis
  • Digital cameras and VMS improve London and Scottish road safety
    March 18, 2016
    London and Scotland are using VMS and digital cameras to successfully lower road deaths. Road safety measures such as variable message signs (VMS) and digital cameras have boosted road safety in the UK capital London and also in the Scottish Highlands. And the systems need not be a drain on electricity supplies. Full matrix driver information signs from SWARCO Traffic, one of the UK’s leading traffic management technology providers, are being installed for the first time across the Transport for London (TfL
  • Lower Thames Crossing gets green light
    March 26, 2025
    The 14.5-mile project near London will include a 2.6-mile tunnel under the Thames River and come at a cost of around £8.3 billion.