Trail blazing for the Gordie Howe Bridge

Gordie Howe International Bridge between Canada and the US will become the first international bridge to link national trail systems across the border.
By David Arminas February 23, 2024 Read time: 3 mins
The Gordie Howe International Bridge, when it opens, will enhance community connectivity and mobility opportunities for all users, according to the Michigan Department of Transportation (image courtesy Windsor-Detroit Bridge Authority)

When open, the Gordie Howe International Bridge will link the Trans Canada Trail with similar US trails, becoming North America’s first bridge to do so.

The Windsor-Detroit Bridge Authority, which will own the new bridge when it opens in September 2025, called the connection of the trails a “first-of-its-kind partnership”. The bridge,  named after a Canadian hockey player who played most of his career in Detroit, will connect the Canadian city of Windsor’s Great Lakes Waterfront Trail to the Iron Belle Trail and Great Lakes Way in Detroit, in the US state of Michigan.

It will be the first international bridge border crossing within Canada’s coast-to-coast 28,000km trail network. Trail users will be able to cross the bridge and make the official border crossing via a multi-use path.

“Enhancing community connectivity and mobility opportunities for all users are among our highest priorities at the Michigan Department of Transportation,” said Bradley Wieferich, director of the department. “This connection between trails across Canada and Michigan is another way the Gordie Howe International Bridge will provide economic and quality of life benefits for generations to come.”

“The Gordie Howe International Bridge is more than a physical connection,” said Charl van Niekerk, chief executive of the Windsor-Detroit Bridge Authority. “It symbolises a shared commitment for sustainable infrastructure to promote economic development, active transportation, tourism and cultural exchange.”

To support the move, Windsor-Detroit Bridge Authority is undertaking public consultation until April to help inform future operational plans for the multi-use path.

“As part of the Trans Canada Trail network, the Gordie Howe International Bridge will be a catalyst for recreation, active transportation opportunities, tourism and economic development in both border communities and beyond,” said Eleanor McMahon, chief executive of Trans Canada Trail.

The Trans Canada Trail is reportedly the longest recreational trail in the world, connecting 15,000 rural and urban communities across every Canadian province and territory. It is a registered charity and work with local partner to build and maintain sections of the trail. Funding comes from the Canadian federal government through Parks Canada and investment from all levels of government and private donors.

Early work for the bridge started in summer 2018 and when completed, it will be the longest cable-stayed bridge in North America. The longest span stretches 853m completely over the river and clearance above water will be 42m. The Canadian government will receive all toll revenues, the project being totally Canadian with no US funding.

The bridge was originally set to open in November 2024, but disruptions due to the COVID-19 pandemic has pushed back the date to September next year and increased costs. The international border crossing will now cost US$4.72 billion, up from around $4.3 billion and is expected to be open in September, a delay of around 10 months.

Windsor-Detroit Bridge Authority is a not-for-profit Canadian Crown corporation created to deliver the Gordie Howe International Bridge project through a public-private partnership. WDBA is responsible for overseeing and managing the construction and operation of the new crossing.

Meanwhile, Bridging North America, BNA, is the main joint venture contractor - Fluor, ACS Infrastructure Canada and Aecon Group - for the design, build, finance, operate and maintain the project.

Jorge Gomez, chief commercial officer for Bridging North America, recently said that the main deck span will be closed by the end of the summer. He called the closeness now of the two halves of the deck - being constructed at the same time - a “little gap” and added that BNA will be “thrilled when it is closed".

For more information on companies in this article

Related Content

  • Canada: Ring of Fire road debate heats up
    September 6, 2016
    A 400km road built specifically into the Canada’s isolated but mineral-rich Ring of Fire region could cost between US$204-$443 million, according to a government-funded study. The road, entirely in the province of Ontario, would start in the port of Thunder Bay at the head of the Great Lakes and run northeast to the James Bay area, just south of Hudson Bay.
  • Texas highway construction project underway
    January 4, 2024
    A US$414 million Texas highway construction project is now underway.
  • Japan gives $3mn for iron bridges in Papua
    January 6, 2023
    Justin Tkatchenko, foreign affairs minister of Papua New Guinea, said the bridges will allow local populations in remote areas to more easily access health care.
  • Massey Tunnel project to be Design-Build-Finance-Operate-Maintain
    January 25, 2016
    The provincial British Columbia government in western Canada has chosen a Design-Build-Finance-Operate-Maintain (DBFOM) procurement model for the Vancouver region’s 10-lane bridge replacement for the ageing Massey Tunnel. The US$2.5 billion project includes a bridge and related Highway 99 improvements between Bridgeport Road in the adjacent city of Richmond and Highway 91 in the city of Delta. The 60-year-old tunnel now carries its limit of 80,000 vehicles a day and is often congested during rush hours.