Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • UK: 50 Years of motorways
    July 6, 2012
    On 5 December, 2008 Britain’s motorway network celebrated its 50th anniversary, and to mark the occasion the Road Users’ Alliance (RUA) published ‘50 Years of Motorways,’ which claims that from a slow and modest start (over 30 years behind its European neighbours) the UK network has never managed to catch up. According to the publication, in the 1960s and early 1970s motorways were viewed as a route to renewal and prosperity. The network made some headway and grew to 2,500km; it crawled a further 1,000km ov
  • SDLG wheeled loaders for Moscow’s new roads and buildings
    March 28, 2014
    Two factories in Russia’s greater Moscow region are using SDLG wheeled loaders to help distribute sand and gravel for use in new roads being built across the region With Russia one of the world’s fastest growing market economies, its need for infrastructure expansion has meant more roads and, as a result, a massive increased need for sand and gravel production. Two sand and gravel factories near Moscow are said to be helping produce the new roads, sidewalks, and also, buildings.
  • Balfour Beatty begins construction of €23.05mn Merseyside motorway link
    January 31, 2014
    Balfour Beatty this week began construction on a €23.05 million (£19 million) scheme to bypass two congested villages and link communities in Sefton along the west coast of Merseyside in Northwest England directly to the M57 and M58 motorways. The road will be 4.5km long and connect the A565 Southport Road to the motorway junction at Switch Island, avoiding the villages of Thornton and Netherton. The newly designated A5758 Broom’s Cross Road will relieve long-standing traffic issues in the area and provid
  • Panama highway rebuilt with concrete
    January 5, 2017
    A highway link to the north of Panama´s capital city that connects with a national park popular with tourists, has now been rebuilt Cement producer and concrete specialist CEMEX carried out a study into the project, to find a cost effective solution. And working with CEMEX, Panama’s Ministry of Public Works began planning for the project in 2015. A 5.7km stretch of the highway has now been improved, with the road structure being built from concrete.