Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Developments in hybrid vehicles
    February 27, 2012
    There is an array of future vehicle solutions in development - Mike Woof reports. Ever since Henry Ford's Model T showed that the motor car could provide transport for ordinary people rather than being an exclusive toy of the rich, vehicle numbers have exploded. In every country around the world, vehicle ownership continues to grow.
  • Nairobi road to nowhere?
    January 3, 2013
    International environmental pressure groups claim a vital road in Kenya goes through parkland as Shem Oirere reports. Kenya’s Nairobi Southern Bypass, a 28.6km stretch has become the second road project in East Africa to run into problems. Designed to the Class A International Trunk Road Standard, the route has been targeted by international environmental pressure groups following Tanzania’s Serengeti Highway, which was derailed last year. The US$208 million bypass will link Mombasa Road, near Ole Sereni Ho
  • Stonehenge Tunnel legal action launched
    December 1, 2020
    Legal action launched against the Stonehenge Tunnel project.
  • Rapid replacement of multiple bridges – the plan
    December 14, 2017
    The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like