Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Tackling Florida’s highway congestion
    August 5, 2016
    Congestion is a major problem in certain areas of US state Florida. Large number of commuters and tourists means that central Florida’s Interstate 4 (I-4) highway suffers particularly from congestion. Its proximity to Disneyland means that the traffic often comes to a complete standstill. A 2012 report from the Texas Transportation Institute ranked Orlando 13th in the US for traffic congestion, with more than 1.5 million daily trips on I-4. The report estimates that each frustrated commuter wastes about 45
  • Slovak government stands firm over R2 Expressway, including Soroska Tunnel
    August 11, 2017
    Jan Durisin, head of Slovakia’s motorway operator NDS, has said that the R2 expressway, will go ahead despite watchdog fears of poor value for money. Completion of the R2, that includes the Soroska Tunnel, remains 2024, he told Slovakian news agencies. NDS, he said, will start looking for a contractor to start work in 2018 on a stretch of the expressway near the town of Roznava. R2 is a 360km route that will run from Kosice in the east across the country to Trenčín, near the Czech border in the west. It wil
  • Massey Bridge concession popular
    October 10, 2016
    The concession package for the Massey Bridge in Canada is proving popular, with several firms keen to win the deal. Three consortia are in the running for the bridge project, which is intended to replace the existing George Massey Tunnel.
  • Kekava Bybass opens with Kapsch technology
    December 5, 2023
    Latvia’s recently opened “high-speed” Kekava Bypass is using Kapsch traffic technology to ensure safety of drivers as they travel between the capital Riga and Lithuania.