Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Southern Ohio Veterans Memorial Highway ready for construction
    April 13, 2015
    Construction is about to start on the first public-private partnership highway project in the US state of Ohio. The Southern Ohio Veterans Memorial Highway, near the city of Portsmouth, will cost nearly US$228 million and is scheduled for completion in 2019, according to the Ohio Department of Transportation (ODOT). The Portsmouth Gateway Group will build the 25.8km, four-lane limited access highway from U.S. Route 23 north of Lucasville to U.S. Route 52 near Sciotoville. An ODOT statement said tha
  • Bentley’s Be Inspired Awards highlight innovation in software use
    January 6, 2015
    Innovation, from design to on-site execution, is alive and well, thanks to a good helping of software application. David Arminas reports from software developer Bentley’s annual global conference, held this year in London Successful project delivery is increasingly about hard men and women using software to get the job done and this year’s global conference in London by US-based software developer Bentley highlighted some innovative - and startling - examples. As usual, the Year in Infrastructure 2014
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • Checking up on the Czech Republic's Via Salis
    May 20, 2022
    Construction of the Via Salis, the Czech Republic’s first public-private partnership for a road project, is on schedule, according to VINCI which is leading the construction and operating consortium.