Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Rajasthan Mega Highways boost trade, tourism
    February 17, 2012
    Rajasthan is one of the most favoured tourist destinations of India for both domestic and international traffic on account of its rich array of historical forts, palaces, art and culture.
  • Colombia: Toyo Tunnel award to be made in September
    July 15, 2015
    The contract award for Columbia’s 9.75km Toyo Tunnel project will be made on September 28, according to Columbian media. The tunnel, costing almost US$760, will be part of a new 39km road between Santa Fe de Antioquia and Canasgordas. World Highways reported in January that the central government will contribute $216 million towards the project, the regional government of Antioquia department will contribute $337 million and the Medellin city government will pitch in with $212 million. Columbia’s N
  • Replace bridge for Vancouver’s Massey Tunnel could aid congestion
    December 21, 2015
    Opponents of a proposed 10-lane bridge near Vancouver, Canada, said the structure will encourage urban sprawl in a region that is already struggling with a booming population. The British Columbia provincial government recently opened the final round of public consultation for the planned 3.3km toll bridge likely to cost around US$2.54 billion.
  • Controversial Russian bridge opens
    August 10, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link having been opened to use by cars and buses. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Russian-manufactured Kamaz truck to reach the city of Kerch.