Smart motorway project for UK’s M3

Balfour Beatty is to work on a €163.5 million (£129 million) upgrade project for a 21.4km stretch of the M3 motorway in the UK. The work involves upgrading the route to smart motorway status and is being carried out for the UK Government’s Highways Agency. This project will increase capacity, reduce congestion and shorten journey times for the 120,000 motorists/day using the route. This section of the motorway runs through the counties of Hampshire and Surrey, between Junction 2 which is interchange with th
July 23, 2014 Read time: 2 mins

1146 Balfour Beatty is to work on a €163.5 million (£129 million) upgrade project for a 21.4km stretch of the M3 motorway in the UK. The work involves upgrading the route to smart motorway status and is being carried out for the UK Government’s 2309 Highways Agency. This project will increase capacity, reduce congestion and shorten journey times for the 120,000 motorists/day using the route. This section of the motorway runs through the counties of Hampshire and Surrey, between Junction 2 which is interchange with the M25 orbital motorway around London and Junction 4a (Fleet). The route will be upgraded to a four-lane motorway by converting the hard shoulder to a permanent running lane. Electronic signs, operated by a regional control centre, will be installed to manage the flow of traffic in response to driving conditions.

Mobilisation work is due to start at the beginning of August. Main construction work is due to start in the third quarter of 2014 with completion scheduled for spring 2017. Construction activity will include installing and refurbishing gantries, new static and variable signs, concrete safety barriers, drainage and surfacing works.

The contract is the latest in a series awarded to Balfour Beatty since the company was appointed to the Highways Agency's National Major Projects Framework in 2010.  In June 2014, Balfour Beatty was awarded the M60 J8 to M62 J20 smart motorway scheme.  In April 2014 the company’s construction joint venture with Skanska completed upgrading a stretch of the M25 to a smart motorway, and in January 2014 Balfour Beatty completed upgrading parts of the M4 and M5 to a smart motorway.

The M3 passes through Chobham Common, one of the largest areas of heathland in Surrey, and   Balfour Beatty’s sustainable design will take into account ecological considerations with natural habitats being reinstated.

M4M5 smart motorway scheme in operation:

Balfour Beatty will use similar technology upgrading the M3 to smart motorway status as it has installed on its successful M4/M5 project

For more information on companies in this article

Related Content

  • Staffordshire road improvements planned
    July 29, 2024
    Staffordshire road improvements will commence shortly.
  • Widening works: road user’s nightmare or operator’s challenge?
    March 14, 2017
    Early - and continuous planning - is essential for successful road widening projects. By Nina Sacagiu, project manager, and Laurent Charles-Nicolas, project director, at Egis. Keeping goods and people moving safely is the primary objective of any transport authority across the world. Delivering this objective on motorways and making the most out of network capacity requires all the resources, skills and ingenuity of those in charge of managing the infrastructure. When the network can no longer cope wit
  • Premium ponds
    April 25, 2012
    A series of balancing ponds are being used to create a sustainable drainage solution on the Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire. Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by Hydro International’s Hydro-Brake Flow Cont
  • Premium ponds
    May 3, 2012
    A series of balancing ponds are being used to create a sustainable drainage solution on the Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire. Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by Hydro International’s Hydro-Brake Flow Cont