Skanska to start Black Cat upgrade

The A428 upgrade work in England was awarded in 2021 to create a 16km dual carriageway to improve journeys between Milton Keynes, Bedford and Cambridge, near London.
By David Arminas November 30, 2023 Read time: 2 mins
A three-tier junction at the Black Cat Roundabout will be among the junction improvements (image courtesy Skanska)

Skanska has secured more funding and will start work on England’s delayed A428 Black Cat highway improvement by the end of the year.

The A428 upgrade work was awarded in early 2021 to create a 16km dual carriageway to improve journeys between Milton Keynes, Bedford and Cambridge, north of London. But a legal challenge by the pressure group Transport Action Network has been delaying work and which has resulted in costs increasing from the original €581 million to €750 million.

Transport Action Network accuses the UK government of having a default solution to traffic congestion that is simply to dual highways, regardless of the increased CO₂ and at the expense of investing in more sustainable public transport such as cycling routes.

Skanska said it has secured nearly €27 million more in funding and the project’s client, National Highways, says work on site can start by the end of this year for the scheme is set to open by 2027. Skanska, working in close collaboration with design partner Mott MacDonald, is responsible for the design and build of the scheme and involve upgrading the route running from the Black Cat roundabout near St Neots to Caxton Gibbet.

A three-tier junction at the Black Cat Roundabout will be among the junction improvements. It will also create better routes for walkers, cyclists and horse riders and deliver better connections to St Neots and its train station. The route is the only remaining stretch of single carriageway between the M1 near Milton Keynes and Cambridge.

Around 25,000 vehicles travel on the A428 between Cambridge Road and Caxton Gibbet every day. But population growth and commercial investments in the area means the volume could reach around 33,000 vehicles by 2040.

Meanwhile, the UK government has allocated €825.3 million for road repairs in south-east England with each local highway authority being given €26.8 million this financial year and a similar amount will be handed over in the 2024/25 financial year. The remaining funding will be provided until 2034. Mark Harper, UK transport secretary, said the funding is part of a national plan to resurface more than 5,000 roads in the next 11 years.

For more information on companies in this article

Related Content

  • £200 million UK road junction project
    March 3, 2025
    Work is going ahead on a £200 million UK road junction project.
  • UK road contracts planned
    December 13, 2021
    Major road contracts are planned for the UK.
  • Tackling the UK's traffic congestion
    February 28, 2012
    The biggest problem on UK roads is congestion, and there is no shortage of ideas as to how it should be tackled. Patrick Smith reports. Congestion (and how to relieve it), along with safety, are among the top priorities facing those responsible for looking after the UK's roads. Road pricing, car-share lanes, greener vehicle initiatives and alternative methods of transport such as buses, trams and rail are all part of the approach, but prior to the current economic climate the nation's love affair with the c
  • Mobile grouting trailers for soil nail rigs
    February 7, 2012
    Geotechnical specialists, Bachy Soletanche and Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England. The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency. The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane