Skip to main content

Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • New German autobahn bridge under constriuction
    May 1, 2015
    Crane manufacturer Manitowoc has supplied six Potain cranes to German contractor Max Bögl. These machines are being used for constructing a new bridge carrying the A3 autobahn, close to Limburg. Working at over 70m high, the cranes tower over the Lahn Valley. The cranes for this project were supplied by Max Bögl’s subsidiary, Max Bögl Transport & Geräte. The three topless Potain MDT 222 cranes were selected for the work as they feature tip heights of up to 76.2m and can operate with a working radius of
  • Italy’s horrific bridge collapse is a sign of a wider problem
    January 7, 2019
    The shocking collapse of a major highway bridge in the Italian city of Genoa has highlighted a major problem with regard to poor infrastructure condition in the country. Causing multiple fatalities, the cable-stayed Morandi Bridge suffered a spectacular failure of a central support. Homes have had to be evacuated and it seems likely that the bridge, opened in 1967, will now have to be demolished. However, warnings had been given. The unusual bridge design, with its thin deck and reinforced concrete stays
  • Major bridge widening project going to plan
    May 2, 2012
    When built it was determined that a vital US road/rail bridge would always be widened.
  • More on the Newmarket Viaduct replacement
    June 15, 2012
    When it was completed in 1965 – just six years after the Auckland Harbour Bridge – the six-lane Newmarket Viaduct with its tall, slender piers was something of an engineering wonder, the first of its kind in the Southern Hemisphere. Forty years on it had become a much-maligned contributor to Auckland’s chronic traffic congestion, too weak seismically to withstand the heaviest loaded trucks let alone a severe earthquake, so narrow in the shoulders that any accident stopped traffic flow and made it difficult