Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Shell’s John Read explains “adaptable bitumen” developments
    December 15, 2016
    Shell’s highly innovative bitumen and asphalt solutions are helping create future-ready urban road networks around the world to meet the needs of today and tomorrow. Shell’s general manager of bitumen technology, Professor John Read, takes a look at some of the company’s game-changing ideas. The next 30 or so years will see a significant transformation in the way we live. Whereas almost 75% of the world’s population lived in rural locations in 1950, around 75% will live in cities by 2050. The global popu
  • Steel for Loch Ba bridge
    February 6, 2012
    Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
  • Cutting road deaths around the world
    February 27, 2020
    A new funding source will help cut road deaths around the world.
  • New tunnel connection for Mexico
    November 8, 2017
    A major tunnel construction project has been carried out in Mexico, setting a technological precedent for Latin America . Mexican materials giant CEMEX took part in the construction of the Coatzacoalcos Underwater Tunnel in Veracruz, Mexico. This innovative project features large tunnel bores and utilised a complex construction process. As a result of these technical challenges CEMEX was required to design and deliver special concretes so as to allow the construction of the different structures needed to