Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Thin surface whitetopping for busy roads
    April 5, 2017
    In the US, considerable experience has been gained with thin white-topping (TWT), with the technique now being used in other countries as well. In the US hundreds of km of TWT is being paved every year, much of it across the mid-western states. A variation of white-topping is being used in Oregon to replace badly rutted asphalt truck lanes on primarily long uphill grades with durable, continuously reinforced concrete pavement (CRCP). Oregon has carried out several of these concrete inlay projects over the
  • Portugal's road safety initiative
    April 12, 2012
    The Portuguese experience with road safety has proved that planning, development, introduction, and hard work do pay off in the end. Paulo Marques Augusto, president of the National Road Safety Authority (ANSR), explained that in the last 10 years a decrease of over 50% has been achieved in the number of fatalities on the road network despite a continuing growth in traffic demand (there are five million vehicles in Portugal), and a similar reduction in travel time on most of the connections between Lisbon a
  • Portugal's road safety initiative
    February 14, 2012
    The Portuguese experience with road safety has proved that planning, development, introduction, and hard work do pay off in the end. Paulo Marques Augusto, president of the National Road Safety Authority (ANSR), explained that in the last 10 years a decrease of over 50% has been achieved in the number of fatalities on the road network despite a continuing growth in traffic demand (there are five million vehicles in Portugal), and a similar reduction in travel time on most of the connections between Lisbon a
  • VIDEO: Explosive bridge demolition in Southern Italy
    February 15, 2016
    Italian contractor General Smontaggi has carried out a successful bridge demolition project in the south of the country. Explosives were used to remove the redundant Viadotto Caffaro Bridge carrying the A3 Autostrade. The 390m long structure had been found to be unsuitable for modern traffic requirements on the route, located in Calabria. The demolition project was not straightforward as the new bridge had already been constructed alongside the redundant structure. The extensive pre-weakening work for the old bridge included cutting into the deck to ensure it collapsed downwards.