Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Cifa gets pumped over final work on Milan bypass
    May 14, 2015
    Truck-mounted concrete pumps from the manufacturer Cifa have been working around the clock at one of Italy’s most prestigious road infrastructure projects, the Milan Outer Bypass. The toll motorway project, known by the TEEM acronym from the Italian name Tangenziale Est Esterna di Milano, involves 32km of new carriageway consisting of three lanes in each direction in addition to an emergency lane. The route winds through agricultural land and connects the A4 highway (Milano-Venezia) in the north to the A
  • State of the art tunnel a conservation triumph
    May 2, 2012
    The opening of a 1.8km tunnel in southern England is designed to ease traffic bottlenecks in an environmentally sensitive area. Patrick Smith reports
  • State of the art tunnel a conservation triumph
    February 28, 2012
    The opening of a 1.8km tunnel in southern England is designed to ease traffic bottlenecks in an environmentally sensitive area. Patrick Smith reports
  • Bentley Systems annual infrastructure awards
    October 25, 2019
    The annual Year in Infrastructure Awards 2019 run by software specialist Bentley Systems saw a record number of entries, with 571 submissions from 60 countries. Competition was tough, with three finalists being selected by panels of expert judges for the wide range of entry categories.