Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Tappen Zee Bridge box seat is the best in the house
    May 21, 2015
    Bridge construction has sometimes been called theatre, with many acts and players building up to a finale. There is no better place to watch good theatre than from a prestigious box seat. This is especially true for the new Tappen Zee Bridge that is taking shape across the Hudson River in the US state of New York. In this case the box seat is just that – a box that sits high atop the old bridge, and it is occupied by a pair of peregrine falcons and their three babies. The family can be seen on-line thanks
  • Giving credence for Clearwater revival
    October 29, 2018
    The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis. There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes. The price tag to demolish and
  • Formwork innovations help bridge building
    July 7, 2015
    A series of formwork developments are helping with challenging bridge construction projects around the world - Mike Woof writes In the Polish city of Krakow, a cost-effective cable stayed bridge is being constructed using a balanced cantilever technique. The current expansion of the Krakow metropolitan railway network (KST) requires the building of a crossing of the Krakow-Plaszow railway junction. Ensuring that daily rail operations remained unaffected during the construction of the 252m long crossing w
  • Complete control of machines using technology
    December 12, 2019
    Sophisticated machine control technology has been utilised on heavy equipment to help deliver a challenging project in New Zealand