Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Us bridges pose cause for concern
    August 2, 2017
    On Aug 1st 2017, it was 10 years since the I-35W Bridge in Minneapolis collapsed. The bridge had been classified as structurally deficient and was undergoing repair at the time. However the repairs focussed on the decking rather than the structure, with the additional weight of the extra asphalt layers and the construction machinery parked adding to the total load and contributing to the collapse.
  • CECE 2018 conference Rome: the sector powers up for digitisation
    March 20, 2019
    Getting the human-machine interface for equipment automation right is a lot trickier than expected. David Arminas reports from the CECE conference in Rome For many contractors, digitisation is key for improving on-site operational efficiency. But it may be time to take stock of progress and examine what does and doesn’t work. That is not to say that the anchors should be thrown out to halt development. Far from it. In the past eight months, the CECE - Committee for European Construction Equipment – led
  • Project AME: the world’s first 3D-printed excavator
    March 7, 2017
    The world’s first 3D-printed excavator was unveiled in the new Tech Experience zone of CONEXPO-CON/AGG. Project AME (Additive Manufactured Excavator), led by Oak Ridge National Laboratory (ORNL) and involving multiple partners from industry, trade associations and academia, was instigated back in 2014 when visiting members of the Center for Compact and Efficient Fluid Power (CCEFP) saw ORNL’s 3D-printed car.
  • Repairing concrete roads using new technology
    July 28, 2015
    In the US state of Arkansas, a key stretch of concrete roads has been improved, allowing it to cope with current traffic volumes.