Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • US DOTs in critical funding battle
    February 9, 2012
    In the US, state DOTs are preparing for the upcoming reauthorisation battle in a tough economic and political climate. Set to expire by the end of the year, the bill is a critical funding source for many transportation projects in the US. However transportation officials in the US are facing a tough battle as the political and economic climate has changed considerably since the last reauthorisation was passed, shortly after President Obama's inauguration in January 2009. Since then, the recession has contin
  • Joy riding
    August 15, 2019
    Our Skidmarks page is highly rated by readers. Your input could help make this page even more entertaining. If you come across any amusing road-related stories or pictures email me at [email protected] JOY RIDING A couple in the US recently took advantage of the self-driving features of a Tesla car for reasons other than transportation. They ignored the suggestions from Tesla to remain alert even when the vehicle was using its self-drive mode and instead engaged in sexual acts, which they recorded on vid
  • A new asphalt plant in Cameroon
    January 27, 2023
    A Lintec CSM4000 containerised asphalt plant in Cameroon has helped with the construction of the country’s first-ever expressway linking its two largest cities, Douala and Yaoundé. The new route replaces an older roadway in use for over three decades that no longer met traffic needs.
  • $220 million New Jersey - Pennsylvania bridge upgrade
    May 14, 2025
    Work is underway for a $220 million New Jersey - Pennsylvania bridge upgrade project in the US.