Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • IRF opens path to its vital world meeting event in Riyadh
    April 3, 2013
    Building on the success of its past World Meetings, International Road Federation (IRF) is poised for its 17th IRF World Meeting & Exhibition, held this year in Riyadh, November 9–13. Hosted by IRF chairman and mayor of Riyadh, Eng Abdullah A. Al-Mogbel, this quadrennial meeting and exhibition promises to be the premier event for global transportation professionals in 2013. Eng Al-Mogbel said this year’s event “will set new global standards of excellence and bring together a wide range of internationally re
  • Temporary bridge replacement in the US
    July 2, 2019
    A temporary bridge structure provided by Acrow Bridge is maintaining traffic flow for a key crossing in Vermont. The bascule bridge is allowing both vehicular and vessel traffic to pass during the reconstruction work to the North Hero-Grand Isle Drawbridge in Vermont. The US$60 million project involves replacing the historic twin leaf bascule bridge on Lake Champlain. This modular steel bascule bridge is allowing transport to continue to and from the Lake Champlain island towns of North Hero and Grand Isl
  • Climbing in Corpus Christi
    September 17, 2020
    The challenge for Doka on the new Harbor Bridge in Texas was to use the same formwork for each pylon despite each pylon’s different geometry.
  • Mexico: underwater tunnel in Latin America
    May 8, 2015
    Mexico will benefit from an important new underwater tunnel - Mauro Nogarin writes. The city of Coatzacoalcos is located at the mouth of the river of the same name, in the Gulf of Mexico, 302km from the city of Salina Cruz, Oaxaca, in the east end of trans-isthmian corridor and at the southern end of Veracruz State. The city is seeing a key development as currently construction is 85% completed on the first immersed tube, underwater tunnel in Latin America. The reasons why experts chose this type of tunne