Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Indonesia toll road completed on schedule
    May 16, 2016
    The construction of the Cipali Toll Road in Indonesia has been completed on time, despite numerous challenges during its construction. The Cipali Toll Road forms part of a larger network, the Trans-Java Toll Road that connects key freeways in Jakarta and beyond. The Trans-Java Toll Road is of enormous importance to Indonesia as it runs for 653km and reduces the existing route by 40km.
  • Manitowoc and Grove brands launching new designs at bauma China 2014
    November 12, 2014
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Manitowoc and Grove brands launching new designs at bauma China 2014
    January 6, 2017
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Simex unveils GEN II of ART 1000 asphalt regeneration tech
    March 6, 2025

    Simex has released the new GEN II version of its ART 1000 patented technology for in-situ regeneration of deteriorated asphalt.

    Simex ART technology focuses on surface-level interventions for the functional recovery of road deterioration. It does not require the removal of milled material or the addition of virgin bituminous mix, instead utilising only the existing on-site material. Most importantly, it avoids the complete interruption of vehicular traffic, ensuring the road is immediately passable after restoration.