Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Crushing and screening innovation for quarries
    November 5, 2012
    Novel crushing and screening developments are coming to market - Mike Woof reports A wide array of innovations and market developments are occurring in the sector for quarrying machinery. New technologies are being introduced while business developments are also changing the face of this market segment. There is strong interest in new technology from industry too and this was well highlighted by data from the organisers of the Hillhead quarry show in the UK. The organisers revealed that there was a jump of
  • Companies line up for Norway’s Rogfast project at Kvitsøy
    November 27, 2018
    Five companies have expressed an interest in the technically challenging €315 million Kvitsøy section of Norway’s major road and tunnel project Rogfast.
  • Sweden’s Tjörnbron Bridge to get replacement cables
    May 30, 2018
    SwedenSwedish contractor Svevia has been commissioned by the Swedish Transport Administration (Trafikverket) to handle cable replacements on the Tjörnbron Bridge. Replacement is expected to start in 2019 for completion by 2025. Svevia project manager Johan Söderberg said the work will be complicated, not least because traffic must continue to us the bridge. He reportedly said that much of the work will have to take place at night, in the summer and in good weather. The 664m-long cable stayed Tjörn Bridge,
  • Gubler gets down with a Kemroc EK 100 chain cutter
    May 1, 2018
    Boulders are usually removed from site by breaking them with a hammer and then using a backhoe to extract the rubble: a time-consuming process. Swiss construction company Gubler, however, used a Kemroc EK 100 chain cutter to cut down on processing time as well as wear and tear on company equipment. With an EK 100 chain cutter mounted on their 22tonne excavator, Gubler excavated the foundations, footings and service trenches in the typical local molasse rock. The project is a large residential complex and