LA1 bridge project faces construction delay

The Department of Transportation and Development in the US state of Louisiana said delay to the US$57.7 million project could be as much as 10 months.
By David Arminas February 9, 2023 Read time: 2 mins
The new bridge over the Intracoastal Waterway is being constructed on the west side of the existing bridge (Louisiana Department of Transportation and Development (LADOTD) and the Lousiana Transportation Authority (LTA))

In the US state of Louisiana, excessive settlement of the piles for the LA 1 replacement bridge in West Baton Rouge could delay the project.

The Louisiana Department of Transportation and Development said in a press release that the construction delay to the US$57.7 million project could be as much as 10 months, according to local media.

The department is working with a contractor on a geotechnical survey to see what might be the best solution. Low-mobility grouting, where grout is injected into the ground beneath the piles to compact loose soils, could be one option.

Work to replace the southbound bridge began in April 2022. The new bridge over the Intracoastal Waterway will be constructed on the west side of the existing bridge. This is part of a two-phased project with contractor Kiewit Louisiana.

The second phase, which could be tendered this summer, will see removal of both existing bridges and construction a northbound bridge, as well as connecting roads on the south side of the bridge. Both bridges will have lanes around 3.7m wide and 3m-wide shoulders.

The bridge replacement project is vital to the nation’s economy, according to a non-political group supporting the project, the LA1 Coalition. LA 1 Highway 1 (LA 1) is the only access to the vast energy resources in the US Gulf of Mexico, notes the coalition. This critical, two-lane highway is the only roadway supporting Port Fourchon – the US’s busiest intermodal energy port, the Louisiana Offshore Oil Port (LOOP) and Grand Isle.

Combined, these locations service over 16 percent of the US’s domestic crude oil production and 4 percent of natural gas production. The highway also supports 20 percent of this nation’s seafood production and eco-tourism destinations like Grand Isle,  Louisiana’s only inhabited barrier island.

 

Related Content

  • Evolution Road gears up in Lund
    March 25, 2021
    The Swedish electric road group, including Elonroad, will install a flatter version of its system.
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)
  • Colombian road contracts being awarded
    May 31, 2021
    A series of Colombian road contracts will be awarded in coming months.
  • Leading private sector companies partner to improve road safety in Morocco
    March 7, 2022
    Coordinated by the International Road Federation (IRF), a group of leading private sector companies active in Morocco entered on 20 December 2021 into a partnership to use their combined knowledge and expertise to reduce road deaths and injuries in the country. This initiative is rooted in the belief that road crashes are largely preventable and road safety is a shared responsibility.