Genoa’s San Giorgio Bridge set to open

Contractor Webuild has been completing work, including solar panel installation.
By David Arminas July 31, 2020 Read time: 1 min
Trucks drive across the San Giorgio Bridge in Italy as part of load testing before the structure opens (photo courtesy Webuild)

The San Giorgio Bridge - the Morandi Bridge replacement in Genoa, Italy - will open on Monday following several weeks of load tests.

The tests started earlier this month following the recent near completion of the structure in a record 13 months by contractors Webuild and Fincantieri. The series of tests, conducted by state motorways entity Anas and Rina initially consisted of 16 heavy trucks driving along the bridge during what is called phase zero of a preliminary assessment.

Later, another 56 trucks lorries weighing 44 tonnes each - a combined weight of 2,500 tonnes - put the bridge through further tests.

Static load tests continued in the coming days trucks continued to run along the bridge. The eastern ramp, however, had remote-controlled vehicles on it in the early parts of the tests.

Meanwhile, Webuild has been completing its work preparing the bridge for delivery, installing glass and solar panels, setting up signage and preparing the final layer of asphalt 4cm thick.

The new bridge was designed by Renzo Piano.

The old Morandi Bridge was named after its structural designer but officially called Viadotto Polcevera, or Polcevera Viaduct in English. It was constructed between 1963 and 1967 along Italy's A10 motorway over the River Polcevera.  It collapsed during a severe storm in 2018, which involved multiple fatalities.

Related Content

  • UK motorway bridge work
    June 10, 2025
    A new bridge now spans the UK’s busy M6 motorway.
  • Doka delivers cantilevering for super-slim piers at Lahntal Bridge
    October 21, 2016
    Doka’s formwork expertise is currently in demand during the construction of one of the busiest motorway viaducts in Germany. The 400m six-lane Lahntal Bridge in Limburg dates from the early 1960s. Every day about 100,000 vehicles cross the bridge that spans the valley of the River Lahn. But traffic loads have increased sharply, so a new bridge is being built sited just a few metres west of the old viaduct. The new Lahntal viaduct will measure a massive 43.5m in width, enabling eight lanes plus hard shoul
  • New M90 surfacing in the UK gain praise
    January 8, 2013
    Early evaluation of surfacing work on the M90 at Rosyth – the first major application of Scotland’s new TS2010 specification – has earned positive praise. Transport Scotland’s determination to obtain pavement that is durable, long lasting and safe (especially in early life) is clearly apparent on the M90 just north of the Forth Road Bridge. Here surfacing has been carried out this spring to TS2010, a tough new specification designed to ensure thin surfacing pavements that work. And the initial prognosis is
  • PPRS Nice 2018: maintenance moves mountains
    June 22, 2018
    Strategic maintenance was a major theme at the second Pavement Preservation and Recycling Summit in Nice, France. The world is changing, mobility is changing and so roads must change and adapt for the future.” With this brief statement, Jacques Tavernier opened the second PPRS Summit. “At the same time there is a growing awareness of poor or non-existent maintenance for highways. The question for this conference is how to adapt road maintenance in the face of this challenge,” said Tavernier, in his role as