Genoa’s San Giorgio Bridge set to open

Contractor Webuild has been completing work, including solar panel installation.
By David Arminas July 31, 2020 Read time: 1 min
Trucks drive across the San Giorgio Bridge in Italy as part of load testing before the structure opens (photo courtesy Webuild)

The San Giorgio Bridge - the Morandi Bridge replacement in Genoa, Italy - will open on Monday following several weeks of load tests.

The tests started earlier this month following the recent near completion of the structure in a record 13 months by contractors Webuild and Fincantieri. The series of tests, conducted by state motorways entity Anas and Rina initially consisted of 16 heavy trucks driving along the bridge during what is called phase zero of a preliminary assessment.

Later, another 56 trucks lorries weighing 44 tonnes each - a combined weight of 2,500 tonnes - put the bridge through further tests.

Static load tests continued in the coming days trucks continued to run along the bridge. The eastern ramp, however, had remote-controlled vehicles on it in the early parts of the tests.

Meanwhile, Webuild has been completing its work preparing the bridge for delivery, installing glass and solar panels, setting up signage and preparing the final layer of asphalt 4cm thick.

The new bridge was designed by Renzo Piano.

The old Morandi Bridge was named after its structural designer but officially called Viadotto Polcevera, or Polcevera Viaduct in English. It was constructed between 1963 and 1967 along Italy's A10 motorway over the River Polcevera.  It collapsed during a severe storm in 2018, which involved multiple fatalities.

Related Content

  • New Genoa bridge project underway
    October 18, 2019
    Work is continuing in the Italian city of Genoa on the massive bridge replacement project. The 50m sections of the new bridge deck are now being raised into place using heavy lifting cranes. The deck sections weigh around 500tonnes apiece and measure 50m long, with 18 of these components being required in all. The bridge replacement work is necessary following the horrific collapse of the old Morandi Bridge during 2018, which involved multiple fatalities. The new bridge was designed by Renzo Piano and the w
  • RINA Consulting starts to lower Morandi Bridge sections
    February 14, 2019
    Deconstruction of the collapsed Morandi Bridge in Genoa, Italy, has begun, according to RINA Consulting. The first bridge deck section was lowered to the ground from a height of 48m, said Roberto Carpaneto, chief executive of RINA which is responsible for design control and construction management of the project. "We are really satisfied with how this delicate operation is being conducted with the whole construction team working as one to guarantee the best result.” RINA Consulting was chosen by the c
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • Italy’s renaissance bridge
    July 21, 2020
    Italian consulting company Italferr created a digital twin for designing the new Genoa bridge and won accolades at Bentley Systems: Bentley Year in Infrastructure Awards