Cost of D1 section Hubova-Ivachnova rises 40%

In Slovakia, the 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than nine years ago.
By David Arminas August 3, 2023 Read time: 2 mins
The Ružomberok bypass project includes the Čebrať Tunnel (image courtesy Slovak National Road Company/NDS)

The cost of the Liptov section of the D1 Hubova-Ivachnova motorway in Slovakia has risen by around 40% to €320 million, according to national media.

The 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than it was nine years ago, the national motorway company NDS is reporting. The D1 Hubova-Ivachnova motorway section should be completed in 2024 compared to the previously planned 2017. The delay was caused by the land slide near the western part of the Čebrať Tunnel.

Earlier this summer, NDS said construction of the D1 between Lietavska Lucka and Dubna Skala in northern Slovakia, which includes the Višňové Tunnel, will be completed within two years.

Meanwhile, Slovakia's Transport Ministry is planning to use funds from the European Connecting Europe Facility programme for preparation of the remaining sections of the D1 motorway. This includes the stretch from Kosice to the border with Ukraine and the R4 expressway from Presov to the Polish border.

The ministry and the NDS will also seek to cover around half of the cost of the northern bypass of Presov's second phase. Slovakia is interested in getting a grant of over €178 million from the Connecting Facility for construction of the second part of the Presov bypass and the remaining R4 sections within the Via Carpatia Corridor.

For more information on companies in this article

Related Content

  • Delays plague Slovakia’s D1 motorway work
    May 12, 2017
    Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50. The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications. Work by the consortium of OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due
  • Boring complete for Slovakia’s Bikos Tunnel
    June 11, 2021
    The 1km tunnel is part of the 4.5km dual carriageway R4 Prešov bypass.
  • Slovakia starts on Presov northern bypass
    August 15, 2019
    Work has started on the first stage of the 4.3km-long Presov northern bypass, part of the R4 speedway in eastern Slovakia.
  • Plans in hand for Slovakia’s longest tunnel
    June 16, 2014
    In Slovakia plans are being made for a new project that will become the country’s longest tunnel when it is complete. Salini Impregilo is the contractor heading the project. The work looks set to cost in the order of €410 million and the project is due for completion in late 2019 or early 2020. Although there was a lower priced bid for the project, this was excluded due to technical problems relating to the proposed tunnel exits. The Visnove Tunnel will measure some 7.7km long and will be constructed in the