Colombia: more money for Toyo Tunnel Project

The Toyo Tunnel Project – the Guillermo Gaviria Echeverri Tunnel Project - covers 18.3km including new roads and is under construction by Consorcio Antioquia al Mar.
By David Arminas April 4, 2024 Read time: 2 mins
The 9.7km-long Toyo Tunnel is the longest in Colombia and running deepest at 900m (image courtesy Gobernacion de Antioquia/Government of Antioquia)

The Colombian government has committed nearly US$144 million to complete the Toyo Tunnel Project in the northwest department of Antioquia.

With a population of around six million, Antioquia is one of the 32 national departments and is located in the central northwest part of Colombia with a narrow section that borders the Caribbean Sea. Most of its territory is mountainous much of which is part of the Andes mountain range.

The Toyo Tunnel Project – also called the Guillermo Gaviria Echeverri Tunnel Project- covers 18.3km connecting the municipalities of Cañasgordas and Giraldo. It includes bridges and the 9.7km-long Toyo Tunnel, the longest in Colombia and running deepest at 900m. It is also is one of many in Colombia’s “fourth-generation (4G) highway network” projects to improve connections nationally.

The Consorcio Antioquia al Mar, a consortium, was awarded the 10-year construction contract in 2015, according to BN Americas, a business intelligence platform that provides information and data solutions to project owners, contractors, suppliers and financial services firms. Consorcio Antioquia al Mar consists of infrastructure contractors Colombiana de Infraestructuras, Carlos Alberto Solarte and CASS Constructores as well as tunnelling civil engineering specialist Estyma Estudios y Manejos

BN Americas  also notes that the agreement between the companies gives Colombiana de Infraestructuras, a subsidiary of Spanish company FCC, 40% ownership and a 20% ownership each for Carlos Alberto Solarte, Estyma Estudios y Manejos and CASS Constructores.

Engineering consultancy WSP worked on final studies and designs in Phase III for Section No. 1 for the consortium. Its work included a transportation study, a soil study for the design of bridge foundations and other retaining structures, a slope stability and stabilisation study, geotechnical study and pavement design, hydraulics analysis and tunnel study and designs.

The consortium also worked with Swedish equipment maker Epiroc for drilling and ventilation strategies. Epiroc's Boomer XE3C and Boomer E2C jumbos with ABC Total Navigation systems have excavated around 1.4 million cubic meters of soil.

For more information on companies in this article

Related Content

  • Colombian tunnel project moving ahead
    May 5, 2015
    The concession package for Colombia’s Toyo Tunnel project will be awarded in the third quarter of 2015. This has been announced by the authorities in Antioquia. The date has been set for September 28th for the concession to be awarded. The project will cost US$530.2 million, with the costs being split between the Medellin Council and the regional government. The 9.8km tunnel will help boost transport and trade between Medellin and Uraba. The regional government has launched a dedicated website with details
  • Azerbaijan road investment topped US$395 million in 2018
    February 15, 2019
    Azerbaijan invested around US$395 million in the repair and construction of almost 1,900 km roads and built road bridge, the government said.
  • Indian road projects underway
    April 20, 2023
    Indian road network development projects are underway.
  • Paving a tunnel at altitude
    September 3, 2021
    A road tunnel stretch that opened for traffic in India in late 2020 is notable for several reasons. The new 9km Atal Tunnel is the world’s longest tunnel at an altitude of higher than 3,048m