Cable works starts on Gordie Howe Bridge

The tolled six-lane bridge over the Detroit River, between Windsor in Canada and Detroit in the US, is costing around US$4.2 billion with an opening date likely in 2025.
By David Arminas February 10, 2023 Read time: 2 mins
Work recently started on the first two of 216 stay cables to be installed on the US side of the 2.5km-long bridge (image courtesy Windsor-Detroit Bridge Authority)

On the Canada-US Gordie Howe International Bridge, installation has begun of the stay cables that will connect the towers to the bridge and road deck.

Work recently started on the first two of 216 stay cables to be installed on the US side of the 2.5km-long bridge with the process for each pair of stay cables taking about two-to-five days. The ends of each metal strand inside the pipe are stressed and anchored to two points – an anchor box inside the tower and an edge girder on the deck. Once a pair of stay cables is securely anchored, workers can move on the next pair in a sequential manner.

The towers and stay cables of the Gordie Howe International Bridge will be capable of supporting nearly 34 million pounds of weight. The tolled six-lane bridge is costing around US$4.2 billion with opening date likely to be 2025.

“With each new stage of construction, the distinctive design of this cable-stayed bridge takes shape,” said Grant Hilbers, vice-president of engineering for the Windsor-Detroit Bridge Authority. “As the stay cables are installed, the Gordie Howe International Bridge’s inspiring, modern and elegant features will become more visible for residents of Windsor [in Canada] and Detroit [in the US].”

The Windsor-Detroit Bridge Authority (WDBA) is a not-for-profit, public-private partanership Canadian Crown corporation created to deliver the Gordie Howe International Bridge project between the Canadian city of Windsor and the US city of Detroit, lying opposite Windsor on the Detroit River. WDBA is responsible for overseeing and managing the construction and operation of the new crossing.

When the bridge is completed, 216 stay cables – 108 pairs – will connect from each tower to the bridge and road deck. Between 38 and 122 metal strands of cable will be fed inside a weather-resistant, high-density polyethylene (HDPE) plastic pipe to make up each stay cable. More than 16,000 metal strands will be used. Once complete, the Gordie Howe International Bridge will be the longest cable-stayed bridge in North America and the tenth

Bridging North America (BNA) became the private-sector partner to design, build, finance, operate and maintain the Gordie Howe International Bridge project in September 2018. BNA includes North American and international companies.

BNA partners have significant experience carrying out major infrastructure projects such as the Herb Gray Parkway in Windsor and also the New Champlain Bridge Corridor and Autoroute 30 in Montreal, Quebec. In the US, BNA constructed  Harbor Bridge, Corpus Christi, Texas, and the Tappan Zee Bridge in New York state.

For more information on companies in this article

Related Content

  • Mersey Gateway Project reaches half-way point across the Mersey
    March 10, 2017
    The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
  • Detroit-Windsor Tunnel crossing gets new customs facilities
    February 17, 2015
    The governments of Canada and the province of Ontario officially opened a new customs plaza at the Windsor-Detroit Tunnel, one of the busiest road crossings between the United States and Canada. The Canadian federal government provided US$8 and the province added $20 million for the project that is part of security improvements and to speed up people processing facilities on the Canadian side of the tunnel. Among the upgrades are new vehicle access lanes, new buildings for the Canada Border Services Agency
  • French bypass project approved
    January 3, 2022
    A French bypass project has been approved for the city of Rouen.
  • New road project underway in Austin, Texas
    April 27, 2023
    Construction work is now underway on a new road project in Austin, Texas.