Breakthrough for Slovenian Karavanke Tunnel

The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
By David Arminas April 2, 2024 Read time: 2 mins
The Slovenian stretch of the second tube alongside the original tube for the Karavanke Tunnel is around 3.5km, while Austria has had to excavate 4.5km (image courtesy Asfinag/DARS)

After three and a half years of excavation, Slovenia has broken through to the Austrian side of the second tube for the 7.9km-long Karavanke tunnel.

It was two years ago that boring on the Austrian side reached the border point with Slovenia, according to Asfinag, Austria’s government-owned company that manages the country’s highways.

The Slovenian stretch of the second tube is around 3.5km while Austria has had to excavate 4.5km.

Turkish tunnelling contractor Cengiz has done the excavation work on the Slovenian side under a contract signed with the Slovenian state-owned motorway company DARS for the €120 million project at the end of January 2020. The European Investment Bank, EIB, soon after lent the project €90 million.

This new tube, alongside the existing one that opened in 1991, should double the capacity of road transport between Villach, Austria, and Jesenice in Slovenia.

Construction of the second tube between the two countries started in August 2020. Delays on the Slovenian side have been attributed to challenging geological conditions, according to DARS.

Slovenia’s infrastructure minister Alenka Bratušek said he anticipates the second tube to open to traffic in 2025. However, after the new tune opens, work will start on renovating the original tube that is expected to be finished in late 2028.

Construction of the original tunnel began in 1986 to connect the Austrian Karawanken Autobahn , the A11, from Villach with the A2 motorway leading to Kranj and Ljubljana in Slovenia. The opening led to fewer vehicles using the historic Loibl/Ljubelj and Wurzen/Korensko sedlo mountain passes.

Early on in the new project, ASFINAG selected to use BIM, Building Information Modeling, for all relevant structural data, compiling a 3D-model as the project progressed.

For more information on companies in this article

Related Content

  • State-of-the art road tunnels in construction and use of ITS
    April 25, 2013
    A wealth of major road tunnel construction projects and significant cant ITS installations within existing key road tunnels have been recently completed or will soon be underway. Guy Woodford examines some of them. A state-of-the art Tunnel Boring Machine (TBM) - the 10th largest ever to be built worldwide will be put to work later this year on New Zealand Transport Agency’s landmark Waterview Connection project in Auckland. The giant Herrenknecht-manufactured machine will be used to construct the twin 2.5
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi
  • VIDEO: Kolin-Kalyon and Limak-Cengiz win North Marmara connector tenders
    May 23, 2016
    Turkey has awarded the much-delayed tenders for the motorway connector roads to Istanbul’s Third Bosphorus Bridge.

    The 90km motorway section between Kinali and Odayeri was awarded to the Kolin-Kalyon joint-venture with completion in seven years and nine months, according to Turkish media reports. The 170km section between Kurtkoy and Akyazi was awarded to Limak-Cengiz joint-venture which will finish the work in six years and nine months.
  • Bosnia: Hranjen Tunnel job to restart
    December 13, 2021
    Meanwhile, Bosnia has set aside money for Zupci and Klobuk border upgrades.