Advanced tolling for Rhode Island

CS America has successfully completed a fast track open road tolling (ORT) project which took just two and a half months to complete, from planning to lane opening, for Rhode Island Turnpike & Bridge Authority (RITBA). The lanes will help maintain traffic flow on this busy thoroughfare over Narragansett Bay, which is host to the 2012 America’s Cup World Series. The work included implementing the CS gantry FastFlow system with attached antennas, lasers, and cameras, as well as interfacing with the existing R
July 10, 2012 Read time: 2 mins
6166 CS America has successfully completed a fast track open road tolling (ORT) project which took just two and a half months to complete, from planning to lane opening, for 6167 Rhode Island Turnpike and Bridge Authority (RITBA). The lanes will help maintain traffic flow on this busy thoroughfare over Narragansett Bay, which is host to the 2012 America’s Cup World Series.

The work included implementing the CS gantry FastFlow system with attached antennas, lasers, and cameras, as well as interfacing with the existing RITBA field system. CS America was able to leverage its experience in similar projects throughout the US and worldwide. The project continues RITBA’s use of the E-ZPass system, while introducing new system features like licence plate image review which is vital to ORT systems.

“We are extremely pleased to offer our community faster travel in time for the summer activities of our tourist season,” said Buddy Croft, RITBA’s executive director. “Our tolling contractor, CS-America stepped up to an extremely tight timeframe and brought the project in on time and on budget, two things as a customer we place a high value on.”

For more information on companies in this article

Related Content

  • Caterpillar smoothens Colombian airport
    August 21, 2013
    Cartagena, Colombia’s coastal city attracts large numbers of visitors, generating heavy traffic through the Rafael Nuñez International Airport. However the surface of the runway had suffered from heavy wear, r esulting in bumpy landings and this was in need of repair. In addition, engineers wanted to create a graded, ramped approach to aid with both take-offs and landings. However, the volume of air traffic using the airport meant that construction work had to take place in a tight timeframe, between mi
  • Last section of Osman Gazi Bridge lifted into place over Izmit Gulf
    May 4, 2016
    The last section of the 3km İzmit Bay Bridge – now officially the Osman Gazi Bridge - was lifted into place on April 21, according to Turkish media. When open later this summer, the bridge will cut the 70-minute drive around İzmit Gulf, on the Sea of Marmara, to just six minutes.
  • 2010 GRAA Winner Profiles
    April 12, 2012
    Our series of profiles on winning projects from the 2010 Global Road Achievement (GRAA) Awards continues with the Construction Methodology Category won by Barrier Systems/Utah Department of Transportation With any major road construction project, the disruption of traffic flow is of paramount concern for engineers, workers and travellers, particularly as it relates to increased traffic delays and the safety of those driving through the work zone. In the state of Utah, USA, work was recently completed on
  • The 95 Express: managing mobility through ITS
    February 17, 2012
    Our series of profiles on winning projects from the 2010 Global Road Achievement Awards (GRAA) continues with the traffic management and intelligent transport systems (ITS) category, won by AECOM for its work on Florida's first managed lanes project