Mallorca Airport upgrade completed

Palma de Mallorca Airport (PMI) reopened its northern runway (06L-24R) at the end of 2020, after completing the surface refurbishment work
September 21, 2021 Read time: 3 mins
The new drainage also forms curves where necessary

The construction project was carried out with the help of MAB Obras Públicas SL and Sampol Ingeniería y Obras, with consulting services from AERTEC. The runway is 3.27km-long by 45m-wide and now also has almost 6,000 linear metres of the new ACO Qmax Neo high-capacity drainage channel for the collection and evacuation of rainwater and wastewater.

Spanish Airports and Air Navigation (AENA) required the northern runway of Palma de Mallorca Airport to meet the highest standards for safety and reliability.

As a result, AENA looked for the replacement of all beacons and existing light signals with LED technology, as well as the renovation of the runway's surface. The switch to LEDs was intended to improve energy efficiency while AENA wanted to improve the runways and build two rapid exit taxiways for aircraft. To increase safety on the runways, the rainwater drainage system was also refurbished to prevent flooding. This new water evacuation system was designed with 8,000 linear metres of maximum-capacity drainage channels, most of which are the new ACO Qmax NEO 300 model.

This system has a circular channel with a diameter of 300mm. This allows the collection of rain and wastewater up to 550litres/second without a gradient. The channels also offer an F900 load rating allowing the units to withstand the passage of aircraft or heavy-duty vehicles.

In addition to collecting water, Qmax allows water to build up within the channel capacity, regulating the volume of water that enters the sewer system and allowing for the effective control of peak flows during a storm. The chosen grate was the cast iron Q-FLOW model. The easy assembly and modularity of the ACO Qmax Neo 300 was also important. Supplied in 2m-long pre-molded pieces that are stackable and transportable, the technicians were able to handle and position the components within the tight timeframe for the refurbishment of the airport.

Drainage has now been improved using the ACO systems
Drainage has now been improved using the ACO systems

In addition to the Qmax drainage channels, 11 high-strength Combipoint PP grates have also been installed on the sides of the runways and 46 circular Multitop cast iron manhole covers.

The ACO DRAIN Qmax Neo is a new member of the ACO Qmax family, which now includes the range of sizes from 150mm, 225mm, 300mm, 350mm up to egg-shaped 550mm, 700mm and 900mm. Integrated gaskets make the channel watertight and all sizes can be combined in a project by tailor-made inlet shafts and inspection elements to meet a project’s hydraulic needs. In case of areas without a terrain gradient, special height adapters can be used to achieve a slope.

A pavement beam provides reinforcement and positioning during installation, while concrete flows through the top part of the product. Installation is simplified with the use of a special jig that keeps the product in place during the process.

For more information on companies in this article

Related Content

  • Revamped concrete runways now in use at Sydney Airport
    November 15, 2013
    Sydney now has a renovated airport runway thanks to contractors Antoun Civil Engineering and Volumetric Concrete Australia. The airport is a major facility as it is the international hub for airlines like Jetstar Airways and Qantas and handles around 37 million travellers each year, with almost 300,000 aircraft movements. Wear was an issue and the decision was made by the Sydney Airport Corporation Limited (SACL) to replace the concrete slabs that make up the runway system. Originally constructed in the 195
  • New and User-friendly PERI UP Scaffolding Components Combine Efficiency and Safety
    June 1, 2021
    The tried and tested components of the PERI UP Scaffolding Kit are now available in optimised form
  • Airport expansion for the Maldives assisted by Trimble
    September 6, 2019
    An airport redevelopment and expansion project in the Maldives has been assisted by the use of technology from Trimble. In 2016 the Chinese firm Beijing Urban Construction Group (BUCG) was awarded the contract for the expansion of the Ibrahim Nasir International Airport on Hulhule island in the Maldives, which is part of the Indian Ocean island group. The massive US$440 million expansion and land reclamation work is intended to boost capacity at the Maldives Airport. BUCG has utilised Trimble field solu
  • Maybe Hire takes on Whorlton Bridge
    March 14, 2025
    For refurbishment of the old English bridge, a temporary cable crane structure - designed by CaSE Civil & Structural Engineering - used a range of Mabey Hire’s propping equipment, including the Mass 50, System 160 and Mat 125 products.