Mallorca Airport upgrade completed

Palma de Mallorca Airport (PMI) reopened its northern runway (06L-24R) at the end of 2020, after completing the surface refurbishment work
September 21, 2021 Read time: 3 mins
The new drainage also forms curves where necessary

The construction project was carried out with the help of MAB Obras Públicas SL and Sampol Ingeniería y Obras, with consulting services from AERTEC. The runway is 3.27km-long by 45m-wide and now also has almost 6,000 linear metres of the new ACO Qmax Neo high-capacity drainage channel for the collection and evacuation of rainwater and wastewater.

Spanish Airports and Air Navigation (AENA) required the northern runway of Palma de Mallorca Airport to meet the highest standards for safety and reliability.

As a result, AENA looked for the replacement of all beacons and existing light signals with LED technology, as well as the renovation of the runway's surface. The switch to LEDs was intended to improve energy efficiency while AENA wanted to improve the runways and build two rapid exit taxiways for aircraft. To increase safety on the runways, the rainwater drainage system was also refurbished to prevent flooding. This new water evacuation system was designed with 8,000 linear metres of maximum-capacity drainage channels, most of which are the new ACO Qmax NEO 300 model.

This system has a circular channel with a diameter of 300mm. This allows the collection of rain and wastewater up to 550litres/second without a gradient. The channels also offer an F900 load rating allowing the units to withstand the passage of aircraft or heavy-duty vehicles.

In addition to collecting water, Qmax allows water to build up within the channel capacity, regulating the volume of water that enters the sewer system and allowing for the effective control of peak flows during a storm. The chosen grate was the cast iron Q-FLOW model. The easy assembly and modularity of the ACO Qmax Neo 300 was also important. Supplied in 2m-long pre-molded pieces that are stackable and transportable, the technicians were able to handle and position the components within the tight timeframe for the refurbishment of the airport.

Drainage has now been improved using the ACO systems
Drainage has now been improved using the ACO systems

In addition to the Qmax drainage channels, 11 high-strength Combipoint PP grates have also been installed on the sides of the runways and 46 circular Multitop cast iron manhole covers.

The ACO DRAIN Qmax Neo is a new member of the ACO Qmax family, which now includes the range of sizes from 150mm, 225mm, 300mm, 350mm up to egg-shaped 550mm, 700mm and 900mm. Integrated gaskets make the channel watertight and all sizes can be combined in a project by tailor-made inlet shafts and inspection elements to meet a project’s hydraulic needs. In case of areas without a terrain gradient, special height adapters can be used to achieve a slope.

A pavement beam provides reinforcement and positioning during installation, while concrete flows through the top part of the product. Installation is simplified with the use of a special jig that keeps the product in place during the process.

For more information on companies in this article

Related Content

  • Innovative, efficient aggregate washing system
    February 22, 2012
    Cleaning the crushed and screened products can boost quality and revenue. Aggregate Processing Solutions has developed a novel washing system aimed at the quarrying sector. The APS-100AT has been developed after almost five years of research and development and is said to be an innovative multi-component material washing system, featuring a highly efficient, heavy duty linear multi-deck screen.
  • Alberta’s peaceful partnership
    May 4, 2020
    A bridge project in northern Canada threw up some unexpected challenges, reports David Arminas, from the banks of the Peace River in Alberta
  • New runway for Philippines airport
    October 1, 2018
    SunWest Construction Development Corporation has been using a concrete paver from Power Pavers at the new Bicol International Airport in the Philippines. The machine has been used to pave a runway, taxiways, and aprons for the US$105 million project underway in the Daraga municipality of Albay province in the Bicol Region. The new facility has been built as a replacement to the single runway Legazpi airport, which is located in an urban area where future expansion is not possible. SunWest used its Powe
  • FPT Industrial’s XCURSOR 13: the legacy of the CURSOR series has never been in better hands
    April 15, 2025
    Unveiled at IAA 2022 in Hannover and shown at the launch of the IVECO Model Year 24 range, the engine further enhances the performance, reliability, and sustainability of one of the longest-running and most renowned propulsion series in on-highway history.