New concrete barrier on key M5 motorway section

Contractor Tarmac has carried out major works on the UK’s M5 motorway after recycling around 30,000tonnes of concrete and providing 8,000m3 of new concrete for new slip-form central barrier works. The project, between Junctions 3 and 4a of the M5, was delivered as part of an eight-week scheme to install 13km of new concrete safety barrier. Approximately 30,000 tonnes of concrete were excavated and then crushed into Type 1 and 6F5 aggregates at Tarmac’s recycling site in Ettingshall, Wolverhampton. Over 14,0
October 30, 2012 Read time: 2 mins
A new section of slipformed concrete barrier has been installed on a stretch of the UK’s M5 motorway for centreline dividing protection
Contractor 2399 Tarmac has carried out major works on the UK’s M5 motorway after recycling around 30,000tonnes of concrete and providing 8,000m3 of new concrete for new slip-form central barrier works. The project, between Junctions 3 and 4a of the M5, was delivered as part of an eight-week scheme to install 13km of new concrete safety barrier.

Approximately 30,000 tonnes of concrete were excavated and then crushed into Type 1 and 6F5 aggregates at Tarmac’s recycling site in Ettingshall, Wolverhampton. Over 14,000tonnes of the recycled aggregates have already been deployed on local construction schemes.

Overnight works saw excavated material transported from the site, stockpiled locally, and reprocessed, with as many as 40 trucks bringing in around 1,700tonnes/night throughout the initiative. Night working was carried out to reduce daytime traffic congestion for road users during peak periods.

Tarmac’s Stourport depot in the West Midlands supplied the concrete for the new barrier which was constructed by Extrudakerb. Tarmac says that recycling materials helps reduce landfill needs, minimises transport and cuts carbon emissions.
According to the firm, this particular project shows its ability to handle large volumes of materials for recycling, while also using this feed to provide high quality recycled and secondary aggregates.

The company’s latest Sustainability Report reveals that, since 2004, the company has reduced waste to licensed disposal by 95%.

For more information on companies in this article

Related Content

  • Key A14 upgrade for the UK to cut congestion
    September 11, 2013
    A joint venture comprising BAM Nuttall and Morgan Sindall will carry out the 4km widening of the UK’s heavily congested A14 route. The €28.5 million (£24 million) project is being carried out for the Highways Agency to reduce journey times more reliable, improve safety and support proposed local development. Mott MacDonald will carry out the design work for the project. Junctions 7-9 of the A14 are highly congested at present due to a combination of heavy commuter traffic and the high percentage of HGVs car
  • Naylor drains away waste water concerns
    January 26, 2017
    A bespoke waste water drainage system saved time and money on a recent UK motorway scheme Work on the London’s M25 motorway Junction 30/A13 Corridor Relieving Congestion Scheme is being undertaken by joint venture contractor Balfour Beatty/Skanska. The project is valued at nearly €91 million and completion is for autumn 2016. There has been a successful continual programme of clean-up using road-sweeper/gulley cleaning trucks to remove detritus from the works areas. Disposal of this type of waste w
  • Reduced emissions, costs, with recycled asphalt
    February 21, 2012
    Recycling is a key issue for asphalt road construction, with many technologies now coming to market. Bith an ever increasing emphasis on sustainability forcing change in the construction sector in Europe and North America, the highway sector now has to seek new solutions.
  • Mobile crushing boosts quarry
    July 19, 2012
    Crushing equipment from Metso is helping boost production and efficiency at the Barrasford Quarry in the UK. Run by Tarmac Quarry products, the operation is now using a Lokotrack LT140 track-mounted mobile crusher, a pair of Lokolink mobile conveyors and several field conveyors. The company is changing the operation from a static to a mobile crushing operation, and it says installing the Metso machinery has helped reduce manpower at the site. The crusher and the conveyors have replaced a pair of static c