VIDEO: Switzerland’s Astra Bridge concept to be tendered

Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from road crews – the Astra Bridge concept. The federal highways agency - FEDRO - will be asking general contractors to submit bids starting this summer for the Astra Bridge system, according to the agency. The system, to be used on motorways, includes ramp sections at each end of what amounts to a train of elevated connected road sections. Vehicles run onto the top of the train which is
May 23, 2019 Read time: 3 mins

Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from road crews – the Astra Bridge concept.

The federal highways agency - FEDRO - will be asking general contractors to submit bids starting this summer for the Astra Bridge system, according to the agency.

The system, to be used on motorways, includes ramp sections at each end of what amounts to a train of elevated connected road sections. Vehicles run onto the top of the train which is positioned directly above where road crews are working. The effect is to create a “bridge” along the length of the lane below upon which paving or maintenance is underway.

The call for tenders will encompass the following services: engineering, production, surveying and control concept, assembly and dismantling concept and finally the operating concept.
 
In order to repair and maintain the heavily frequented motorways in metropolitan regions, work has to be carried out at night to an ever-increasing extent. The required closures of traffic lanes increasingly give rise to congestion, even during the night. To prevent this, intervention times are periodically revised and frequently must be reduced to the detriment of roadwork projects.

The time slots for the implementation of roadworks permit only short construction phases and are also a risk factor in terms of quality and worker safety. In addition, the installation and removal of the temporary safety barriers that are required for night-time work costs valuable time and money, notes FEDRO.

FEDRO said it has carried out a feasibility study concerning a specially designed mobile ramp that accommodates two lanes of traffic.

A roadwork site with a width of 5.2m and a length of 100m can be set up beneath the ramp which can be raised hydraulically. The ramp can also be moved both longitudinally and laterally.

Moving the ramp system over a distance of 100m should take between 10-20 minutes, says the agency. It must be possible to assemble the drive-on and drive-off sections in the course of one night. The remainder of the ramp can be extended during a second night to a length of 238m.

To avoid indentations in the road surface, the loads can be borne by large insulated base plates.

FEDRO says it wants the system to be operational by 2022.

The e-mail address for companies interested in submitting a bid is: %$Linker: 2 Email <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-email [email protected] false mailto:[email protected] true false%>

Astra’s vital statistics

Number of traffic lanes: 2
Length: 238m, but extendable using modular sections
Width: 7.3m
Maximum incline (drive-on/drive-off sections): 6.1%
Clearance in travel direction: 5.2m x 3.1m
Lateral clearance: 2.2m x 3.1m
Weight: around 1,200tonnes
Moving speed: around 0.5kph


Related Content

  • Versatile and efficient, Sennebogen’s new port crane offers high performance
    January 6, 2017
    Sennebogen’s 875 E-Series crane is said to offer a high materials handling capacity, with low energy requirements and operating costs. Efficiency has been increased due to a new energy recovery system. Various gantry or pylon solutions and variable cabin elevation features are available. This materials handling machine has an operating weight of up to 150tonnes and is suited for port handling and industrial applications. A newly developed energy recovery cylinder is being implemented for the first time. The
  • Versatile and efficient, Sennebogen’s new port crane offers high performance
    March 27, 2013
    Sennebogen’s 875 E-Series crane is said to offer a high materials handling capacity, with low energy requirements and operating costs. Efficiency has been increased due to a new energy recovery system. Various gantry or pylon solutions and variable cabin elevation features are available. This materials handling machine has an operating weight of up to 150tonnes and is suited for port handling and industrial applications. A newly developed energy recovery cylinder is being implemented for the first time. The
  • Getech’s versatile sludge treatment solution
    April 5, 2013
    Due to an innovative and strong frame design and the use of premium raw materials and components, Getech/Gennaretti centrifuges can be employed across mining, tunnelling, petroleum and chemical industry-based sludge treatment processes. They can also be built in mobile plants on containers, easy to transport to remote areas and quick to install, able to manage sludge volumes going from 5 to 150m³ per hour.
  • TRA 2014 attracts healthy abstracts and invited session numbers
    August 6, 2013
    The call for abstracts and invited sessions for the 5th Transport Research Arena TRA 2014 event has proved “very successful”, according to organisers. A total of 1,100 abstracts and 110 invited sessions were submitted ahead of the event being held on April 14-17 in Paris La Défense. The deadline to submit accepted full papers is September 30, 2013 (for notified authors only). A new call is now open for "Outreach Marketplaces" (posters only), and the submission deadline is October 31, 2013. Innovative compan