VIDEO: Switzerland’s Astra Bridge concept to be tendered

Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from road crews – the Astra Bridge concept. The federal highways agency - FEDRO - will be asking general contractors to submit bids starting this summer for the Astra Bridge system, according to the agency. The system, to be used on motorways, includes ramp sections at each end of what amounts to a train of elevated connected road sections. Vehicles run onto the top of the train which is
May 23, 2019 Read time: 3 mins

Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from road crews – the Astra Bridge concept.

The federal highways agency - FEDRO - will be asking general contractors to submit bids starting this summer for the Astra Bridge system, according to the agency.

The system, to be used on motorways, includes ramp sections at each end of what amounts to a train of elevated connected road sections. Vehicles run onto the top of the train which is positioned directly above where road crews are working. The effect is to create a “bridge” along the length of the lane below upon which paving or maintenance is underway.

The call for tenders will encompass the following services: engineering, production, surveying and control concept, assembly and dismantling concept and finally the operating concept.
 
In order to repair and maintain the heavily frequented motorways in metropolitan regions, work has to be carried out at night to an ever-increasing extent. The required closures of traffic lanes increasingly give rise to congestion, even during the night. To prevent this, intervention times are periodically revised and frequently must be reduced to the detriment of roadwork projects.

The time slots for the implementation of roadworks permit only short construction phases and are also a risk factor in terms of quality and worker safety. In addition, the installation and removal of the temporary safety barriers that are required for night-time work costs valuable time and money, notes FEDRO.

FEDRO said it has carried out a feasibility study concerning a specially designed mobile ramp that accommodates two lanes of traffic.

A roadwork site with a width of 5.2m and a length of 100m can be set up beneath the ramp which can be raised hydraulically. The ramp can also be moved both longitudinally and laterally.

Moving the ramp system over a distance of 100m should take between 10-20 minutes, says the agency. It must be possible to assemble the drive-on and drive-off sections in the course of one night. The remainder of the ramp can be extended during a second night to a length of 238m.

To avoid indentations in the road surface, the loads can be borne by large insulated base plates.

FEDRO says it wants the system to be operational by 2022.

The e-mail address for companies interested in submitting a bid is: %$Linker: 2 Email <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-email [email protected] false mailto:[email protected] true false%>

Astra’s vital statistics

Number of traffic lanes: 2
Length: 238m, but extendable using modular sections
Width: 7.3m
Maximum incline (drive-on/drive-off sections): 6.1%
Clearance in travel direction: 5.2m x 3.1m
Lateral clearance: 2.2m x 3.1m
Weight: around 1,200tonnes
Moving speed: around 0.5kph


Related Content

  • Putzmeister adds five-section pump
    January 6, 2017
    Putzmeister has added a five-section 38m, 160m3/hr concrete pump, which can be used to place loads inside buildings some 3m higher than the four-section option. Built on a 26tonne chassis, the new 38.5 can reach heights of 31m while leaving the final boom section to pass inside the building. In common with the company’s other machines, the 38.5 now has outrigger sensing, which feeds into the control system and prevents the boom from extending/slewing if the outriggers are not fully deployed. The machine als
  • Putzmeister adds five-section pump
    April 19, 2013
    Putzmeister has added a five-section 38m, 160m3/hr concrete pump, which can be used to place loads inside buildings some 3m higher than the four-section option. Built on a 26tonne chassis, the new 38.5 can reach heights of 31m while leaving the final boom section to pass inside the building. In common with the company’s other machines, the 38.5 now has outrigger sensing, which feeds into the control system and prevents the boom from extending/slewing if the outriggers are not fully deployed. The machine als
  • Hi-viz hijinks make a flockery of saftey clothing
    September 16, 2015
    Fashionable they aren’t, but the wearing of high-visibility clothing is increasingly either recommended by businesses or made mandatory by law, especially for construction workers on every kind of site. But has the use of “hi-vis” clothing, especially the vest, gone too far? In Britain, the wearing of the hi-viz clothing has taken off - literally, according to a BBC television news report that shows a flock of chickens wearing the fluorescent coloured vest.
  • World Highways requires new reporter
    August 8, 2014
    We are looking for a bright and tenacious international business reporter to write news and features in our expanding portfolio of award-winning and market-leading business-to-business publications. The role will require you to report on international road policy, highway planning, design and construction, as well as a variety of senior management and safety issues. See our website: www.worldhighways.com