Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Second giant moveable scaffolding system set for Mersey Gateway
    May 4, 2016
    A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
  • Volvo CE’s earthmovers on film for promotion campaign
    October 25, 2018
    For its new publicity campaign, Volvo Construction Equipment has teamed up with film star hardman Dolph Lundgren to showcase its excavators’ endurance in a stunt-filled mini-movie entitled Pump It Up. In the tongue-in-cheek mini-movie Lundgren, whose credits include Rocky IV, Universal Soldier and The Expendables, plays an all-action drill instructor in an excavator boot camp determined to test the diggers to their limits. Excavators ranging from 1.5t to 95t are ordered to do press-ups, pull-ups, flip
  • Improved soil compactors developed by BOMAG
    February 11, 2013
    Boppard based BOMAG is unveiling its new 5-8tonne class soil compactors, which are said to offer increased performance and lower running costs. Compact, manoeuvrable and economical the BW145 and BW177 machines are said to be highly productive and suited to use on small-medium size projects. High performance is claimed for compaction, gradeability and efficiency and Judith Rheingans of the firm said, “The operator platform has been redesigned to give better visibility and access. The operator can see the dru
  • Gordie Howe Bridge progresses with community support money pledged
    June 18, 2019
    The Windsor-Detroit Bridge Authority and other agencies involved in the US$4.25 billion Gordie Howe International Bridge have pledged millions of dollars in community support. WDBA, contractor Bridging North America, the US state of Michigan and the federal Canadian government announced the support plan, which involves more than 30 agencies and organisations, according to a report by the Canadian Broadcasting Corporation. The plan includes a $15 million Neighbourhood Infrastructure Strategy for both s